The 836 billion VND Exhibition Center project in Ho Chi Minh City has not been completed after 10 years of construction and needs to be repaired

MINH QUÂN |

HCMC - The Ho Chi Minh City Exhibition Center Project with more than VND836 billion under construction for 10 years is degraded and needs to add a survey package to prepare a repair plan.

The information is stated in the official dispatch that the Department of Finance has just sent to the Ho Chi Minh City People's Committee, after appraisal the submission of the Management Board of Investment and Construction Projects for Civil and Industrial Works (investor of the Ho Chi Minh City Planning Exhibition Center project).

Previously, the investor proposed to add a package worth nearly 491 million VND to survey and evaluate the overall status of the project, and at the same time make a detailed estimate for items that need to be repaired or replaced due to damage after a long period of stagnation.

After appraisal, the Ho Chi Minh City Department of Finance said that the addition of this package does not increase the total investment of the project and is in accordance with current regulations. On that basis, the Department of Finance recommended that the Ho Chi Minh City People's Committee consider and approve the additional bidding package according to the investor's proposal.

The Ho Chi Minh City Planning Exhibition Center project was built in the Thu Thiem New Urban Area (old Thu Duc City), with a scale of 5 floors, with a total investment of more than 836 billion VND.

The project has a unique architecture of two teams leaning against each other, using many steel structures to create triangles, and is expected to become a public project with a symbolic status of the area.

The building has the function of displaying and exhibiting urban architectural plans, and is also a place to organize events and exchange between experts, people and tourists.

Trung tam trien lam quy hoach TPHCM xay 10 nam chua xong.  Anh: Anh Tu
The Ho Chi Minh City Planning Exhibition Center has not been completed after 10 years of construction. Photo: Anh Tu

The project started in 2015 with the City Planning Exhibition Center Construction Project Management Board as the investor, including 49 packages, including 18 construction packages, equipment signed in the form of a complete package, without a general contractor.

By 2018, the project had completed the rough construction and begun the equipment installation phase. However, since June 2018, the project has had to temporarily stop construction due to problems in the XL6 package (production and installation of outside covering items such as glass walls, facades, support frames, railings, ceilings and metal decorative panels). The reason is that the contractor did not perform in accordance with the signed contract, affecting the entire progress of the related packages because there was no construction site.

In March 2024, after the project was transferred to a new investor, the Project Management Board for Investment and Construction of Civil and Industrial Works, the contract with the contractor of package XL6 was officially terminated. The investor has replaced it with a new construction unit to gradually restart the project.

However, according to the investor's report, the "shelving" of many years has caused many items and equipment of the project to seriously deteriorate, requiring careful inspection to have a basis for repair or replacement.

In addition, some equipment of the packages, although imported to the construction site before, has not been installed yet, and the manufacturer's warranty period has now expired, and the quality needs to be re-evaluated.

In October 2024, the investor proposed that the total cost arising in 16 packages of the project was nearly 77 billion VND.

However, the Ho Chi Minh City Department of Construction believes that this number does not have enough basis to consider. The reason is that the accurate determination of the repair and replacement value of damaged items requires an independent consulting unit to conduct surveys, assessments and make detailed estimates.

MINH QUÂN
TIN LIÊN QUAN

Ho Chi Minh City is about to inaugurate a 2,000-seat circus with an investment capital of nearly VND1,400 billion

|

HCMC - After more than 2 years of construction, Phu Tho Circus and Multi-purpose Performance has completed about 99% of the volume and is expected to be inaugurated at the end of August 2025.

Workers busy at the 800 billion VND project in Thu Thiem

|

HCMC - After 11 years of being "shelved", the HCMC Planning Exhibition Center in the new urban area of ​​Thu Thiem has officially resumed construction.

No alcohol or drug concentration was detected in the driver who caused the accident on Kham Thien Street

|

The incident of a pickup truck losing control caused a series of accidents in Hanoi, injuring 1 person and damaging 9 motorbikes, the driver was negative with alcohol and drug levels.

The circulation of storm No. 3 caused heavy damage in many provinces, thousands of people were evacuated

|

Bac Ninh, Hung Yen, Nghe An, Thanh Hoa... recorded serious damage to people and property due to heavy rain, thunderstorms and landslides from the circulation of storm No. 3.

20h News: Pain and tears for losing property due to floodwaters

|

powerlessly seeing all their assets lost in floodwaters; Inside the illegal gold mine in the middle of Quang Tri forest, the army surveyed to destroy...

More than 200 houses in a border commune of Nghe An were destroyed by floods

|

Nghe An - Affected by storm No. 3, major floods have severely damaged and swept away 231 houses in the border commune of My Ly.

Checking food at Unico Global YB Company after the case of a foreign object that giong nhu a robot in a rice tray

|

Lao Cai - The Provincial Labor Federation has just inspected food and meal quality at the Company and discovered unusual foreign objects in the workers' rice tray.

People cried, helpless to see their house about to collapse next to floodwaters

|

Nghe An - On the afternoon of July 23, 3 households in Vinh Hoan village (Con Cuong commune) had a house that was deeply flooded almost to the roof, tilted to collapse with floodwaters, making them cry.

Ho Chi Minh City is about to inaugurate a 2,000-seat circus with an investment capital of nearly VND1,400 billion

MINH QUÂN |

HCMC - After more than 2 years of construction, Phu Tho Circus and Multi-purpose Performance has completed about 99% of the volume and is expected to be inaugurated at the end of August 2025.

Workers busy at the 800 billion VND project in Thu Thiem

Tâm Tú |

HCMC - After 11 years of being "shelved", the HCMC Planning Exhibition Center in the new urban area of ​​Thu Thiem has officially resumed construction.

Hiện trạng Trung tâm triển lãm 800 tỉ đồng trên "đất vàng" Thủ Thiêm sắp khởi động lại

HỮU CHÁNH |

Sau 10 năm khởi công, dự án Trung tâm triển lãm quy hoạch TP Hồ Chí Minh đạt hơn 80% tiến độ, song không thể hoàn thành, nằm trơ trọi giữa khu "đất vàng" Thủ Thiêm.