Railway overpass on Hanoi Ring Road 4 takes shape

Sóng Hữu |

Hanoi - The railway overpass under package 8 of Ring Road 4 has taken shape, and is expected to be completed in sync with the parallel road in the near future.

In addition to the construction of a parallel road, package No. 8 (building a parallel road of Ring Road 4 through the old Soc Son and Me Linh districts, Hanoi) also stipulates the construction of 3 overpasses on the route including the Ca Lo River overpass, the Hanoi - Lao Cai railway overpass and the Hau village bridge.

Of these, the Hanoi - Lao Cai railway overpass is the largest bridge built under package No. 8. The project is about 560m long with 27 spans, the width of the bridge deck on each side is 15m.

According to Lao Dong on July 8, the railway overpass has now taken shape. At the construction site, many machines and workers are mobilized to construct the remaining items of the project.

Currently, there are 2 spans left on the left of the route waiting to install the last girder platforms. The installation of the remaining 2 spans will be implemented after the contractor completes the repair of the service road.

Speaking to Lao Dong Newspaper reporter, Mr. Nguyen Hoai Nam - Head of technical department, Construction Management Board of Ring Road 4 in the Capital Region, Truong Son Construction Corporation - said that up to now, the most difficult part of the railway overpass project has been basically completed.

"After completing the installation of the remaining 2 girder spans, the contractor will move to the completion stage. This phase will not take too much time" - Mr. Nam said.

The contractor is also ensuring the construction progress of the remaining 2 bridges in package 8, including Ca Lo and Hau village bridge. The main items have been basically completed by this time.

Regarding the overall progress of the entire package No. 8, Mr. Nam said that up to this point, the contractor consortium has completed about 70% of the construction volume, ensuring progress compared to the plan.

"It is expected that in July, the contractor will hand over the last 2 sections of the route. Machinery, personnel, and raw materials have been prepared by the contractor. When the site is clear, the construction work will immediately be implemented" - Mr. Nam said.

It is expected that by September 2025, package No. 8 (construction of the Ring Road 4 parallel road through the old Soc Son and Me Linh districts) will be completed, 3 months ahead of schedule as required by the City People's Committee.

s
The Hanoi - Lao Cai railway overpass, part of package No. 8 - construction of the Ring Road 4 parallel road, has taken shape. Photo: Song Huu
s
The project has 27 spans, of which 25 have been girded. Photo: Song Huu
a
The remaining two spans will be girded in the coming time. Photo: Song Huu
s
The railway overpass has basically completed the main items. Photo: Song Huu
Loi vao cau duoc rao chan bang ton. Anh: Song Huu
The entrance to the bridge is fenced with corrugated iron. Photo: Song Huu
s
Workers working at the construction site. Photo: Huu Chanh
s
The bridge girder has been cast at the construction site. Photo: Song Huu
s
The bridge over the Ca Lo River has also basically completed the main items. Photo: Song Huu
s
Image of Hau village bridge under construction. Photo: Song Huu
Duong song hanh Vanh dai 4 doan qua xa, TP Ha Noi. Anh: Song Huu
According to Hanoi's request, the Ring Road 4 parallel road will have to be completed in 2025. Photo: Song Huu
Sóng Hữu
TIN LIÊN QUAN

Hanoi is about to start construction of 2 bridges across the Red River on Ring Road 4

|

Hanoi - It is expected that in 2025, the city will start construction of the Hong Ha and Me So bridges across the Red River on Ring Road 4.

Belt 4 Hanoi is sprawled with the front of the handover

|

Hanoi - Chairman of the City People's Committee assigns districts and districts to complete land acquisition for belt 4 before 15.4 but so far many segments have not been liberated.

Hanoi has 2 weeks left to hand over enough land to build Ring Road 4

|

Hanoi - Districts must complete site clearance for the Ring Road 4 project before April 15 according to the direction of the Chairman of the City People's Committee.

The accident between 2 passenger buses on the Vinh Hao - Phan Thiet highway, 34 people have been discharged from the hospital

|

Lam Dong - There have been 34 victims in the particularly serious accident on the Vinh Hao - Phan Thiet Expressway discharged from the hospital.

Gold price today 7.9: Massive plummet, down 400,000 VND/tael

|

Gold price today 7.9: After a recovery session, the gold market plummeted in today's trading session.

Car crashes into multiple people, injuring 6 in Hanoi

|

Hanoi - A car crashed into many motorcyclists, only stopping when it crashed into a tree on the sidewalk.

36-year-old tourist dies after parachuting in Da Nang

|

Da Nang has just had a paragliding accident in the Son Tra mountain area, killing a tourist.

Admire the giant Bryde whale hunting for prey in Nhon Ly sea

|

Gia Lai - Giant Bryde whale suddenly appeared hunting for prey in Nhon Ly sea area (Quy Nhon Dong ward) creating a spectacular scene.

Hanoi is about to start construction of 2 bridges across the Red River on Ring Road 4

HỮU CHÁNH |

Hanoi - It is expected that in 2025, the city will start construction of the Hong Ha and Me So bridges across the Red River on Ring Road 4.

Belt 4 Hanoi is sprawled with the front of the handover

HỮU CHÁNH |

Hanoi - Chairman of the City People's Committee assigns districts and districts to complete land acquisition for belt 4 before 15.4 but so far many segments have not been liberated.

Hanoi has 2 weeks left to hand over enough land to build Ring Road 4

HỮU CHÁNH |

Hanoi - Districts must complete site clearance for the Ring Road 4 project before April 15 according to the direction of the Chairman of the City People's Committee.