Dong Thap focuses on solutions to speed up the progress of the Cao Lanh - An Huu expressway

Phong Linh |

Dong Thap - Provincial leaders requested relevant units to increase human resources and equipment to speed up the construction progress of the Cao Lanh - An Huu expressway.

Dong Thap Electronic Information Portal reported that on the morning of October 9, Vice Chairman of the Provincial People's Committee Tran Van Dung inspected the construction progress of Component Project 2 of the Cao Lanh - An Huu Expressway Construction Project, Phase 1. Thereby, he requested the units to focus on solutions to speed up the construction progress.

Component project 2 is about 11.45 km long, with a preliminary total investment of more than VND 3,850 billion, with the People's Committee of Tien Giang province (now the People's Committee of Dong Thap province) as the managing agency. To date, the project's construction value has been completed by more than 53%.

Pho Chu tich UBND tinh Dong Thap Tran Van Dung kiem tra thuc te tai vi tri vuong mat bang. Anh: Cong thong tin dien tu Dong Thap.
Vice Chairman of Dong Thap Provincial People's Committee Tran Van Dung inspected the site at the site. Photo: Dong Thap Electronic Information Portal.

Currently, the project is facing obstacles due to the entanglement of 02 medium-voltage power lines, which are the 220kV Cai Lay - Cao Lanh high-voltage line affecting the construction of Ba Huong bridge; the 500kV Song Hau - Duc Hoa high-voltage line affecting the construction of Danh Cuu bridge.

In the face of the above situation, Vice Chairman of the Provincial People's Committee Tran Van Dung requested relevant units to increase human resources and equipment to speed up the construction progress of the entire route, especially at the intersection with the Trung Luong - My Thuan expressway; it is necessary to specifically assess the progress of each item, proactively develop a detailed construction plan, and determine a clear timeline to ensure general progress and technical quality.

Dai dien lien danh nha thau bao cao tien do du an
Representative of the contractor consortium reports the progress of component project 2 of the Cao Lanh - An Huu Expressway Construction Project, phase 1. Photo: Dong Thap Electronic Information Portal.

Mr. Dung requested the Provincial Civil and Industrial Construction Investment Project Management Board to review and synthesize the investment needs for residential access routes for construction; at the same time, coordinate with relevant units to determine appropriate technical solutions for construction to speed up progress at locations with land clearance problems, before relocating the power system.

Phong Linh
RELATED NEWS

Dong Thap achieves many breakthrough results in economy and transportation

|

Dong Thap - Average economic growth (GRDP) for 5 years reached 5.51%. GRDP per capita is estimated at about 85.5 million VND.

Accelerating the construction of the Cao Lanh - An Huu Expressway, ensuring technical traffic opening at the end of the year

|

Dong Thap - The provincial Chairman requested to focus equipment and human resources on the construction of the Cao Lanh - An Huu expressway to ensure technical traffic opening by the end of this year.

Unusual landslides on the coast wash away entire snail pond

|

Quang Tri - The sticky rice has not yet reached harvest time, but unusual coastal erosion has gradually engulfed each pond, causing farmers in My Thuy commune to restless.

Efforts to "eras the book" of waste in Hue City after the flood

|

HUE - The armed forces coordinated with environmental workers to clean up the huge amount of waste remaining after the flood.

2 Generals, 1 Senior Lieutenant General, 1 Colonel of the army receive new assignments

|

2 Generals, 1 Senior Lieutenant General, 1 Colonel of the army have just been transferred, assigned, and appointed to new positions last week (from November 3-7).

The predecessor of Typhoon No. 14 Fung-wong is about to strengthen into a super typhoon, preparing to make a first landfall

|

Typhoon Fung-wong (called Uwan in the Philippines) is continuing to strengthen into a super typhoon and is heading towards the first landfall area.

Continue the beautiful journey under the roof of Viet Duc High School

|

The 70th anniversary of the founding of Viet Duc High School was attended by one of the first students studying at the school in 22, now 90 years old. Mr. Nguyen Kim Son used to hold the position of Director of the Department of Science - International Cooperation of the General Department of Land Use of Vietnam, and was once the secretary of the General Secretary of the Lao People's Revolutionary Party - Kaysone Phomvihane.

Top 5 Vietnam Idol 2016: Singer at a young wedding party of Son Hai Group, a private person

|

Looking back at the career of Top 5 Vietnam Idol 2016, including the romantic singer who just sang at the wedding of young master Son Hai Group and Dinh Tu's wedding.

Đồng Tháp đẩy mạnh phân cấp khi triển khai chính quyền địa phương 2 cấp

Phong Linh |

Đồng Tháp - Ngày 8.10, UBND tỉnh ban hành Kế hoạch tiếp tục đẩy mạnh phân cấp quản lý nhà nước khi triển khai vận hành chính quyền địa phương 2 cấp.

Dong Thap achieves many breakthrough results in economy and transportation

Tùng Linh |

Dong Thap - Average economic growth (GRDP) for 5 years reached 5.51%. GRDP per capita is estimated at about 85.5 million VND.

Accelerating the construction of the Cao Lanh - An Huu Expressway, ensuring technical traffic opening at the end of the year

Phong Linh |

Dong Thap - The provincial Chairman requested to focus equipment and human resources on the construction of the Cao Lanh - An Huu expressway to ensure technical traffic opening by the end of this year.