Gia Lai races to speed up disbursement of public investment capital

THANH TUẤN |

Gia Lai - The construction progress of many projects is slow, so the disbursement rate of public investment capital in the province is lower than the national average.

On October 2, the Standing Committee of the People's Council of Gia Lai province, term XII (2021 - 2026) held a question-and-answer session between two sessions.

In which, the delegates presented the reasons for the slow disbursement of public investment capital. According to Mr. Dinh Huu Hoa - Deputy Director of the Department of Planning and Investment of Gia Lai province, the Provincial People's Committee has issued many documents directing the implementation of basic construction work.

However, the disbursement rate of capital from the State budget is still lower than the national average. As of September 17, Gia Lai province has disbursed nearly VND 1,675 billion, reaching 37.8% of the total capital plan for 2024.

Among them, there are many projects that have not been disbursed or the disbursement rate is lower than the national average. The reason is that the investors are still in the final bidding stage to approve the project, then sign the implementation contract...

Nhieu du an o tinh Gia Lai bi cham tien do do thieu cat, soi...Anh: Thanh Tuan
Many projects in Gia Lai province are behind schedule due to lack of construction materials. Photo: Thanh Tuan

The shortfall in land use fees has made it impossible to implement many projects using this source of capital. Therefore, there are projects that have volume but cannot pay for completed volume.

Currently, the lack of raw materials, soil, sand, gravel, etc. is one of the main reasons why projects are behind schedule and contractors are sluggish and stuck.

Some districts in Gia Lai proposed that the Provincial People's Committee soon direct specialized agencies to appraise and submit for approval the land mine planning in the area to facilitate the exploitation of land resources for filling projects.

However, the approval process for land mines is currently lengthy and complicated, requiring the opinions of the Department of Natural Resources and Environment and relevant agencies. This leads to delays in project appraisal and approval.

In addition, there is a situation where land mines have been removed from the planning of 3 types of forests but are stuck in the mechanism and have not been handed over to local management.

According to Mr. Dinh Huu Hoa - Deputy Director of the Department of Planning and Investment of Gia Lai province, the province strives to achieve a disbursement rate of over 95% by the end of the year. To achieve this, the province must focus on removing obstacles in compensation and site clearance.

Gia Lai Provincial People's Committee also directed to strictly handle responsibilities for investors, units, groups and individuals who are slow to implement tasks, affecting the province's disbursement progress.

THANH TUẤN
RELATED NEWS

7-vehicle chain collision on Phan Thiet - Dau Giay expressway causes congestion

|

Dong Nai - A series of 7 car accidents on the Phan Thiet - Dau Giay highway caused traffic congestion and damaged vehicles.

Venezuelan President escorted to New York prison

|

Venezuelan President Nicolas Maduro was escorted to a prison in Brooklyn, New York, USA on the evening of January 3.

Long Thanh airport installs equipment, completes terminal worth 35,000 billion VND

|

Dong Nai - Long Thanh Airport is continuing to complete and install passenger terminal equipment, after opening the first flight.

Hanoi traffic is locally congested on the last day of the 2026 New Year holiday

|

Hanoi - Ending 4 days of New Year's Day holiday 2026, crowds from all provinces and cities flocked to Hanoi, causing localized traffic congestion in many areas.

Suspension of work for tour guide who incorrectly introduced Lam Kinh Relic Site

|

Thanh Hoa - Due to incorrect introduction of part of the explanation about the Lam Kinh Special National Relic Site, a female tour guide was suspended from work.

Large tonnage trucks "destroy" Provincial Road 16 in Hue

|

HUE - Large truck convoys carrying soil and rocks have "crowed up" Provincial Road 16, seriously affecting people's travel.

Unusualities at Tao Quan 2026

|

Tao Quan 2026 has had personnel changes when director Khai Anh left VTV from the beginning of 2025.

Motorbike taxi drivers drive at full capacity, expecting strong income increase

|

Hanoi - On the last day of the New Year holiday, many technology motorbike taxi drivers expect high income increases.

Ca Mau allocates 38,510 billion VND of public investment capital

NHẬT HỒ |

Ca Mau - The above amount is allocated for investment in the period 2026-2030 so that this province can break through to develop quickly and sustainably.

Kien Giang plans to invest more than 139,000 billion VND in public investment in 5 years

NGUYÊN ANH |

Kien Giang - The expected medium-term public investment plan for the 2026-2030 period in the province is more than 139,300 billion VND, allocated to 847 programs and projects.

Reasons why Vinh Phuc is slow to disburse public investment capital

Bảo Nguyên |

By September, the disbursement of public investment capital in Vinh Phuc had only reached more than 3,998 billion VND, equal to 51.4% of the capital plan assigned by the Central Government.