On September 29, information from the Khanh Hoa Provincial Inspectorate said that in the first 9 months of 2025, the unit has implemented an inspection plan to ensure on- schedule.
In particular, the Provincial Inspectorate has urgently deployed inspections of 128 works and projects with signs of difficulties, problems, delays, prolonged backlogs or low efficiency, and risks of causing loss and waste.
Regarding the inspection content, it focuses on state management, socio-economic management of units and localities and compliance with the law of organizations and individuals in all fields.
During the period, the whole industry has conducted 70 inspections, including 29 transfers from the previous period and 41 new inspections.
Thereby, inspection conclusions have been issued for 55 inspections at 92 units.
The inspection results discovered economic violations with an amount of more than 57 billion VND and 15,355m2 of land.
The inspection agency has recommended recovering and paying the State budget more than 56 billion VND, reclaiming 15,355m2 of land, and recommending other handling of 711.18 million VND.
Transfer the two cases to the investigation agency and discipline 4 related individuals.
In the first 9 months of the year, the Khanh Hoa Provincial Inspectorate also monitored and urged 46 inspection conclusions. The total amount of money recommended to be recovered to the State budget is more than 72 billion VND, and to date more than 43 billion VND has been collected.