On December 19, some sections of Ho Chi Minh City Ring Road 3 must be technically opened to traffic

PHẠM ĐÔNG |

The Deputy Prime Minister requested to focus on the sections of Ho Chi Minh City Ring Road 3 with a plan to complete and technically open some sections on December 19.

On October 1, the Government Office announced that it had just issued Notice No. 526/TB-VPCP on the conclusion of Deputy Prime Minister Mai Van Chinh at the working session of Inspection Team No. 7 on reviewing and removing difficulties and obstacles related to key transport projects planned to be completed in 2025 to achieve the target of 3,000km of expressway.

According to the announcement, the project implementation results still have some shortcomings and limitations.

The task of relocating high-voltage power has not been completed on time on September 15: there are still 8 locations in Dong Nai (component project - DATP 3), 1 location in Ho Chi Minh City (DATP 5), 1 location in Tay Ninh (DATP 7).

Regarding construction: DATP 3 and DATP 5 are still 4-10% behind in contract value; about 4.6km of DATP 5 has not yet been guaranteed.

The capital disbursement task in 2025 is still very slow: the entire project has only reached about 36% of the plan.

The task of studying the additional investment plan for Tan Van intersection has just stopped at the reporting step, there is no official decision to speed up the progress.

To ensure the basic completion of the project in 2025, the Deputy Prime Minister requested Ho Chi Minh City and the provinces of Dong Nai and Tay Ninh to launch a 100-day and night peak emulation campaign; direct investors and contractors to focus on accelerating construction, closely following the basic completion schedule in 2025, ensuring quality, without losing money.

Direct relevant agencies to promote acceptance, payment, disbursement, striving to complete the 2025 plan according to the direction of the Prime Minister.

Ho Chi Minh City completes the relocation of high-voltage power at Tan Van intersection (although not affecting construction, but striving to complete in October 2025); urgently completes the investment plan for Tan Van intersection; restore the progress to compensate for the slow output, speeding up the construction progress of the 4.6km DATP 5 section.

Direct relevant agencies to focus and coordinate support in ensuring traffic at Tan Van intersection in conditions of both construction and exploitation, avoiding congestion, creating conditions to speed up progress.

Dong Nai province must complete the handover of the site and complete the relocation of 8 high-voltage power pole locations in October 2025; direct the contractor to restore the slow production compensation schedule for DATP 3.

Tay Ninh province completed the relocation of the remaining high-voltage power location at Km90+615 in October 2025; speeding up the construction of the final items of DATP 7.

For investors of DATPs, the Deputy Prime Minister noted that the remaining construction volume of the project is large; however, the remaining time is very short, it is necessary to be more determined, increase human resources, equipment, organize "3 shifts, 4 teams" to complete on schedule.

In which, focusing on sections planned to be completed and technically opened to traffic on December 19 in accordance with the set goals.

The provinces of Dong Thap, Vinh Long, Dong Nai continue to ensure timely supply of materials for the project.

The Deputy Prime Minister requested the Ministry of Construction to monitor and urge the implementation progress of the Ho Chi Minh City Ring Road 3 project; monthly synthesize and report to Deputy Prime Minister Mai Van Chinh, Head of Inspection Team No. 7.

PHẠM ĐÔNG
RELATED NEWS

Prime Minister directs handling of erosion on 10,853 billion VND expressway

|

The Prime Minister assigned the Minister of Construction to inspect and handle the erosion on the Vinh Hao - Phan Thiet expressway, and report the results before September 25.

Permanent Deputy Prime Minister directs handling of slow-progressing contractors in 4 expressway projects

|

The Permanent Deputy Prime Minister directed to remove difficulties for 4 expressway projects, promptly handle contractors who were behind schedule and violated regulations.

Deputy Prime Minister directs to remove 4 obstacles at the Ho Chi Minh City Ring Road 3 project

|

The Deputy Prime Minister requested the Ho Chi Minh City People's Committee and relevant localities to focus on removing difficulties and obstacles in the Ring Road 3 project.

This week, there is a plan to arrange public service units and state-owned enterprises

|

The Minister of Home Affairs said that he is completing the plan to reorganize public service units, reorganize state-owned enterprises and within the organizational structure of the ministries.

The friendship between the people of Vietnam and the Russian Federation will develop better and better

|

Chairman of the Central Committee of the Vietnam Fatherland Front Do Van Chien believes that the Comprehensive Strategic Partnership between Vietnam and the Russian Federation, as well as the friendship between the two peoples, will increasingly develop well, trust and support each other.

Remaining bodies found in the fish pond burst in Lao Cai

|

Lao Cai - The fish pond break in Bao Thang commune caused 4 workers to be swept away, including 2 deaths.

Lao Cai streets are flooded with mud, soil, and garbage after the water recedes

|

Lao Cai - After the water receded, local people and authorities urgently cleared mud, soil, and waste to restore traffic and daily activities.

Prime Minister approves 2 Vice Chairmen of Quang Ngai Provincial People's Committee

|

The Prime Minister approved the election results of 2 Commune Secretaries, Mr. Do Tam Hien and Mr. Nguyen Cong Hoang, to hold the position of Vice Chairman of the Quang Ngai Provincial People's Committee.

Prime Minister directs handling of erosion on 10,853 billion VND expressway

PHẠM ĐÔNG |

The Prime Minister assigned the Minister of Construction to inspect and handle the erosion on the Vinh Hao - Phan Thiet expressway, and report the results before September 25.

Permanent Deputy Prime Minister directs handling of slow-progressing contractors in 4 expressway projects

PHẠM ĐÔNG |

The Permanent Deputy Prime Minister directed to remove difficulties for 4 expressway projects, promptly handle contractors who were behind schedule and violated regulations.

Deputy Prime Minister directs to remove 4 obstacles at the Ho Chi Minh City Ring Road 3 project

PHẠM ĐÔNG |

The Deputy Prime Minister requested the Ho Chi Minh City People's Committee and relevant localities to focus on removing difficulties and obstacles in the Ring Road 3 project.