The Government Inspectorate concluded that the project inspection had difficulties and problems in Quang Ninh province

TRÍ MINH |

The Government Inspectorate issued Document No. 363/KL-TTCP, Concluding the inspection of inspection of projects with difficulties and problems in Quang Ninh province.

The conclusion stated that in Inspection Decision No. 675/QD-TTCP, there are 3 projects, including: Ha Long Ocean Park Project invested by Ha Long Sun Limited Liability Company; FLC Ha Long Convention Center Complex, Service Area, Resort and Resort villa project invested by FLC Group; Thanh Cong Viet Hung Automobile Factory Project invested by Thanh Cong Viet Hung Industrial Park Joint Stock Company.

Of the above 3 projects, 2 projects have been inspected and examined by competent authorities, including: Ha Long Ocean Park Project; Conference Center Complex Project, Service Area, Resort and Resort villa FLC Ha Long.

Based on the records, documents and regulations in Clause 1, Article 31 of the 2025 Law on Inspection; Document No. 7864/VPCP-V.I dated August 22, 2025 of the Government Office on reporting and proposing a scope of thematic inspection for works and projects with difficulties and problems; Plan No. 1505/KH-TTCP dated July 22, 2025 of the Government Inspectorate on thematic inspection of works and projects with difficulties, problems, prolonged delay, low efficiency, risk of loss and waste (Decision No. 874/QD-TTCP dated August 29, 2025).

Regarding the Thanh Cong Viet Hung Automobile Factory Construction Investment Project invested by Thanh Cong Viet Hung Technology Complex Industrial Park Joint Stock Company, the project has completed the construction investment and put the project into operation to produce and trade passenger cars from March 2025; by July 2025, the project has produced 674 cars (commercial products) for sale.

Through the inspection, it was shown that the Investor had basically fully and in accordance with legal regulations on a number of contents in project investment implementation.

The recommendations of Thanh Cong Viet Hung Industrial Park Joint Stock Company are mainly related to the lack of preferential policies for investment in construction, production and assembly of cars in industrial parks such as in the Economic Zone, there are no difficulties or obstacles in project investment.

On February 10, 2025, the Government issued Decree No. 21/2025/ND-CP amending and supplementing Article 9 of Decree No. 26/2023/ND-CP, accordingly, a number of recommendations of Thanh Cong Viet Hung Technology Complex Industrial Park Joint Stock Company were resolved.

Up to now, the People's Committee of Quang Ninh province has determined that the project has no difficulties or problems.

Regarding the proposal for handling measures, the Government Inspector General recommended determining the land rental price for one-time payment within the project content.

The Government Inspectorate recommended that the People's Committee of Quang Ninh province direct relevant specialized agencies to urgently determine the one-time land rental price for an area of 1,443.2 m2 of land; coordinate with Thanh Cong Viet Hung Technology Complex Industrial Park Joint Stock Company to complete the land lease dossier and financial obligations for 1,443.2 m2 of land according to the provisions of law.

The Government Inspectorate also recommended that the Ministry of Finance consider removing the Thanh Cong Viet Hung Automobile Factory Project from the list of projects with difficulties and problems.

TRÍ MINH
RELATED NEWS

Strengthening inspection and examination of occupational safety and hygiene

|

Vice President of the Vietnam General Confederation of Labor Ngo Duy Hieu suggested that it is necessary to strengthen inspection and examination of occupational safety and hygiene (OSH) in the coming time.

Mr. Nguyen Quoc Doan holds the position of Deputy Inspector General of the Government Inspectorate

|

Mr. Nguyen Quoc Doan - Deputy Chief Justice of the Supreme People's Court - was appointed to the position of Permanent Deputy Inspector General of the Government Inspectorate.

Report the inspection results of projects with problems under the management of the Ministry of Industry and Trade

|

The inspection of projects with difficulties and problems under the management of the Ministry of Industry and Trade is carried out according to Decision No. 696/QD-TTCP of the Government Inspectorate General.

Supplying drinking water and food to help Gia Lai people after the storm

|

Gia Lai - After the storm, floods swept away the spillway, isolating hundreds of households.

Personnel transfer and appointment in Thanh Hoa, Nghe An, Cao Bang, Quang Tri

|

The provinces of Thanh Hoa, Nghe An, Cao Bang, Quang Tri... have just implemented decisions on assigning, mobilizing, and appointing personnel.

Union Newsletter: Safety solutions for workers against online recruitment scams

|

Worried about being scammed out of high salaries, workers invite each other to find jobs directly; Coal industry with the goal of increasing income for workers

The Government Inspectorate concluded that the project inspection had difficulties and problems in Quang Ninh province

|

The Government Inspectorate issued Document No. 363/KL-TTCP, Concluding the inspection of inspection of projects with difficulties and problems in Quang Ninh province.

Arsenal share regrettable points at Sunderland's field

|

In the early morning of November 9 (Vietnam time), Sunderland and Arsenal held each other to a score of 2-2 in round 11 of the Premier League 2025-2026.

Strengthening inspection and examination of occupational safety and hygiene

LƯƠNG HẠNH |

Vice President of the Vietnam General Confederation of Labor Ngo Duy Hieu suggested that it is necessary to strengthen inspection and examination of occupational safety and hygiene (OSH) in the coming time.

Mr. Nguyen Quoc Doan holds the position of Deputy Inspector General of the Government Inspectorate

PHẠM ĐÔNG |

Mr. Nguyen Quoc Doan - Deputy Chief Justice of the Supreme People's Court - was appointed to the position of Permanent Deputy Inspector General of the Government Inspectorate.

Report the inspection results of projects with problems under the management of the Ministry of Industry and Trade

TRÍ MINH |

The inspection of projects with difficulties and problems under the management of the Ministry of Industry and Trade is carried out according to Decision No. 696/QD-TTCP of the Government Inspectorate General.