Nearly 2,000 workers work day and night to clear the North-South expressway first section

Bích liên |

Nearly 2,000 workers and hundreds of machines and equipment are working day and night on the entire Huu Nghi - Chi Lang expressway (Lang Son), striving for the goal of opening the route by the end of 2025, completing the entire project in 2026.

Started on April 21, 2024, the Huu Nghi - Chi Lang border gate expressway has a total length of 60 km and an investment of over VND 11,000 billion, with a scale of 4 lanes. Stretching through 4 districts, cities and 16 communes of Lang Son province, this expressway directly connects with 3 international border gates: Huu Nghi, Coc Nam and Tan Thanh.

Anh: Viet Trung
Photo: Viet Trung

The starting point is at Km1+800 (National Highway 2.1 route) connecting with the road to Huu Nghi border gate (in Dong Dang town, Cao Loc district, Lang Son province); the end point is at Km44+749.67 (Bac Giang - Lang Son expressway route) in Mai Sao commune, Chi Lang district, Lang Son province. The project is the first section on the North - South expressway axis.

Another section of the Huu Nghi - Chi Lang project is the route connecting Tan Thanh border gate and Coc Nam border gate (connecting Huu Nghi - Chi Lang expressway with Dong Dang - Tra Linh expressway) 17 km long, with a scale of 02 lanes (14.5 m wide roadbed).

Anh: Viet Trung
Photo: Viet Trung

In order to achieve the goal of opening the route in 2025 and completing it in 2026, the project is currently focusing on 1,955 personnel and 683 machines and equipment, implementing the construction of 55 locomotives simultaneously. The construction output to date has reached 12.3% of the contract.

Since the groundbreaking ceremony, Lang Son province has handed over 49.9/59.87 km of ground (reaching 83.6%). According to the report of the Ministry of Construction, the land clearance has been implemented by Lang Son province urgently, but so far the project has not been completed to build resettlement, relocation, improvement of high voltage roads and handing over the entire ground to the investor.

On the entire Huu Nghi - Chi Lang route, there are a total of 38 bridges of all kinds across provincial roads and rivers and streams.

Anh: Viet Trung
Photo: Viet Trung

At the Km41+000 girder casting site, workers are implementing the casting of SuperT girders for 3 overpasses Km41+450, Km41+825, Km42+825 bridges under the EC03. According to the representative of DNDA, the girder casting work still ensures a plan of 20 films/month.

Mr. Tran Van Chuan, Deputy Director of the Huu Nghi - Chi Lang Expressway Project Management Board, said that contractors are currently focusing on mobilizing all human resources and equipment, implementing the spirit of "one site handover, urgently implementing construction as soon as possible".

Anh: Viet Trung
Photo: Viet Trung

Entering the night shift, at the construction site, many bulldozers, road rollers and trucks are operating to serve the construction of roadbed and dumping. Due to the large volume of excavated excavated areas, contractors are mobilizing maximum technical personnel and equipment to speed up the progress.

According to calculations, the Friendship - Chi Lang project needs 2.6 million m³ of stone, 13.8 million m³ of embankment and must be discharged 8.4 million m³. The People's Committee of Lang Son province has approved 43 dumping yards with a reserve of 4.4 million m³, lacking 4.0 million m³, DNDA with advice, the contractor is conducting a survey to propose additional dumping for the project. For the approved waste yards for the project, the DNDA proposed the local priority to the land clearance of urgent, completed and handed over in the first quarter of the first quarter of 2025.

Anh: Viet Trung
Photo: Viet Trung

A representative of DNDA said that contractors have mobilized additional machinery, equipment, and human resources to speed up the project's construction.

To meet the goal of completing the route by the end of 2025 according to the Prime Minister's direction, in the remaining 8 months with a large workload, it is determined that there needs to be determination and synchronous efforts from all relevant parties.

Bích liên
TIN LIÊN QUAN

Proposal to renovate the key national highway Dak Lak to Phu Yen

|

Dak Lak - The competent authority has proposed that the Central Government request to renovate and upgrade National Highway 29 connecting the locality with Phu Yen province.

A series of key expressways focus on accelerating to the finish line early

|

Despite many difficulties such as lack of raw materials, construction sites of key projects such as Chau Doc - Can Tho - Soc Trang, Khanh Hoa - Buon Ma Thuot are all operating extremely busily as localities, investors and contractors are all making efforts to speed up construction progress to ensure the set goals.

Pouring 51 billion VND into resettlement of Huu Nghi - Chi Lang expressway project

|

Lang Son - The Provincial People's Committee has approved 21 bidding packages with a total value of more than 51 billion VND to serve the Huu Nghi - Chi Lang expressway.

Reasons for choosing Bac Giang City as the administrative center of Bac Ninh province after the merger

|

Bac Ninh - The project to reorganize Bac Ninh and Bac Giang provinces clearly states the reasons for choosing Bac Giang city as the administrative center after the merger.

Updated gold price at the end of session 19.4: Shocking decrease, risks still lie

|

Updated gold price at the end of the session on September 19: Domestic gold prices decreased by up to 6 million VND/tael. The risk is still tiem nang when the difference between buying and selling is too high.

Nghe An has many options for naming new communes after the arrangement

|

Nghe An - Some localities named new communes after districts with serial numbers, some other localities named them with historical and traditional cultural elements.

The Ministry of Public Security informs about new features on VNeID for flying

|

The VNeID application has just integrated a new feature to serve passengers getting on a plane from buying tickets, going through security checkpoints... the entire process without paperwork.

List of 65 expected commune-level administrative units in Thai Binh after the reorganization

|

Thai Binh - According to the draft project, after the arrangement, the whole Thai Binh province will now decrease from 242 to 65 commune-level administrative units.

Proposal to renovate the key national highway Dak Lak to Phu Yen

Bảo Trung |

Dak Lak - The competent authority has proposed that the Central Government request to renovate and upgrade National Highway 29 connecting the locality with Phu Yen province.

A series of key expressways focus on accelerating to the finish line early

PHƯƠNG ANH - TRUNG TUẤN |

Despite many difficulties such as lack of raw materials, construction sites of key projects such as Chau Doc - Can Tho - Soc Trang, Khanh Hoa - Buon Ma Thuot are all operating extremely busily as localities, investors and contractors are all making efforts to speed up construction progress to ensure the set goals.

Pouring 51 billion VND into resettlement of Huu Nghi - Chi Lang expressway project

Khánh Linh |

Lang Son - The Provincial People's Committee has approved 21 bidding packages with a total value of more than 51 billion VND to serve the Huu Nghi - Chi Lang expressway.