110 billion VND for 2km of town road in Tuyen Quang

Việt Bắc |

Tuyen Quang - After 2 years of construction and having to adjust the progress, more than 2km of Son Duong town road with a total investment of 110 billion VND is about to be completed.

The 13B road project extending from Quyet Thang residential group to Mang Ngot residential group, Son Duong town was started in February 2023 with a total investment of 110 billion VND, invested by the Son Duong District Construction Investment Project Management Board.

The contractor is 27/7 Company Limited. With a length of more than 2km, this route will be completed in 12 months. However, due to some problems arising, after 2 years of construction, the new project is now in the completion stage.

Recorded at the beginning of May 2025, the entire length of the road surface has been paved with asphalt concrete, lighting systems have been installed. Items such as sidewalks and drainage are under construction.

Viec thi cong keo dai toi hon 2 nam, tuyen duong 13B hien sap hoan thanh. Anh: Viet Bac.
The construction has lasted for more than 2 years, and Son Duong Town's route 13B is now nearing completion. Photo: Viet Bac.

Mr. Le Van Toan (Son Duong town) said that this route opens up new development space for the town, making travel between residential groups safe when not having to go through National Highway 37.

"In 2024, there will be a lot of rain, so construction will stop at some point. We also hope that the road will be completed soon and handed over so that people can move conveniently," said Mr. Toan.

The 13B extended road project has been reopened according to urban road standards with items such as sidewalks, trees, lighting, and a synchronously designed drainage system.

Informing reporters, a representative of the Son Duong District Construction Investment Project Management Board said that route 13B has a longer construction period than expected due to problems in site clearance and the need to adjust some construction items.

"In addition, the project lacks on-site fill soil, forcing the contractor to transport soil remotely, causing costs and construction time to be adjusted. Currently, only a few small items remain, and the project is expected to be handed over for use in the second quarter of 2025," informed the Son Duong District Construction Investment Project Management Board.

Some recorded images.

Tuyen duong tu trung tam thi tran Son Duong voi diem cuoi giao cat voi QL.37 theo huong di Thai Nguyen. Anh: Viet Bac.
The route from the center of Son Duong town with the end point intersecting with National Highway 37 towards Thai Nguyen. Photo: Viet Bac.
Mat duong toan tuyen da duoc tham be tong nhua. Anh: Viet Bac.
The road surface of the entire route has been paved with asphalt concrete. Photo: Viet Bac.
Mot so hang muc phu tro nhu via he, he thong thoat nuoc dang duoc thi cong.
Some auxiliary items such as sidewalks and drainage systems are under construction. Photo: Viet Bac.
Khu vuc dau tuyen duong thuoc to dan pho Quyet Thang van ngon ngang vat lieu xay dung. Anh: Viet Bac.
The area at the beginning of the route in Quyet Thang residential group is still littered with construction materials. Photo: Viet Bac.
Tuyen duong mo moi theo tieu chuan duong noi thi. Anh: Viet Bac.
The new road is opened according to the standards of inner-city roads. Photo: Viet Bac.
Việt Bắc
TIN LIÊN QUAN

Spending 10 billion VND to build nearly 3 years without completing 284m of road in the town

|

Cao Bang - The inner-city road connecting Group 2 - Group 3 (Trung Khanh town) has been under construction for nearly 3 years but has not been completed.

Tourism to the source in Tuyen Quang attracts visitors during the holidays

|

Tuyen Quang - The Tan Trao National Historical Site Complex, the red address on the journey back to the source, is of interest to many tourists, especially young people during the holidays.

The billion-dong roads connecting Tuyen Quang and neighboring areas

|

Tuyen Quang - Routes with a total investment of thousands of billions of VND are expected to synchronize traffic infrastructure, promote economic and social development.

Mai Linh Nha Trang driver continues to call for help due to prolonged unpaid wages and benefits

|

Khanh Hoa - The collective of workers requested Mai Linh Nha Trang Company Limited to completely resolve unpaid wages, social insurance debts...

Upcoming inspection of the purchase and sale and transfer of shares of banks

|

The State Bank said it will pay attention to inspecting the contents of share ownership ratio; buying, selling, transferring bank shares, and granting credit.

The Law on Health Insurance will be amended, moving towards free medical examination and treatment for people

|

The health sector is orienting to amend the Law on Health Insurance, to specify some contents towards free medical examination and treatment for people under the direction of General Secretary To Lam.

Ho Chi Minh City Party Secretary Nguyen Van Nen has a new task

|

HCMC - Secretary of the HCMC Party Committee Nguyen Van Nen is the head of the Steering Committee for the development of the HCMC urban railway network system.

Metro No. 1 in Ho Chi Minh City asks to postpone construction by another year despite commercial operation

|

HCMC - The HCMC Urban Railway Management Board (MAUR) proposed that the HCMC People's Committee adjust the completion time of Metro Line 1 project to the end of the fourth quarter of 2025.

Spending 10 billion VND to build nearly 3 years without completing 284m of road in the town

Nhóm PV |

Cao Bang - The inner-city road connecting Group 2 - Group 3 (Trung Khanh town) has been under construction for nearly 3 years but has not been completed.

Tourism to the source in Tuyen Quang attracts visitors during the holidays

Việt Bắc |

Tuyen Quang - The Tan Trao National Historical Site Complex, the red address on the journey back to the source, is of interest to many tourists, especially young people during the holidays.

The billion-dong roads connecting Tuyen Quang and neighboring areas

Lam Thanh |

Tuyen Quang - Routes with a total investment of thousands of billions of VND are expected to synchronize traffic infrastructure, promote economic and social development.