On January 8, the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board) reported to the Ho Chi Minh City People's Committee on the progress of completing and opening 10 projects from now until Lunar New Year 2025.
There are 2 projects that will hold inauguration and traffic opening ceremonies, including:
Hang Bang Canal Upgrade and Renovation Project (District 5): The inauguration ceremony will take place at 8:00 a.m. on January 17, 2025.
New construction project of Tan Ky - Tan Quy bridge: Opening ceremony will be held at 8:00 a.m. on January 20, 2025.
There are 5 projects that will simultaneously open to traffic at 8:00 a.m. on January 20, 2025 (no ceremony will be held):
Project to upgrade and expand Hoang Hoa Tham Street (Tan Binh District).
Construction of the Tran Quoc Hoan – Cong Hoa connecting road: Open traffic from Phan Thuc Duyen underpass (the beginning of the route) to Hoang Hoa Tham, and simultaneously complete all 3 connection points from the route to Terminal T3 (above and below ground).
The remaining section (from Hoang Hoa Tham to the end of the route) is expected to be handed over before February 20, 2025 and completed and opened to traffic before April 30, 2025, ready to serve Terminal T3 which will come into operation on April 30, 2025.
Project to upgrade and expand Luong Dinh Cua Street: Open to traffic from Nguyen Hoang to Tran Nao intersection. However, some areas near the intersection will continue to be under construction due to delays in site clearance.
Project to upgrade and expand Duong Quang Ham street: 1 of the entire route will be opened to traffic and phase 2 will be opened to traffic (the entire cross-section will be open to traffic) after the City Electricity Corporation completes the undergrounding and relocation of electric poles on April 30, 2025.
New Tang Long Bridge construction project: One unit opened to traffic.
The new Ba Hom bridge construction project will open the entire main bridge to traffic on January 26, 2025.
At the An Phu intersection project (Thu Duc City), the Ba Dat bridge and Giong Ong To 2 bridge have both been completed but not yet put into operation. They are expected to open to traffic along with the entire An Phu intersection on December 31, 2025.
In addition, the construction project of Nguyen Van Linh - Nguyen Huu Tho intersection (District 7) will complete all work on the roofs of HC1 and HC2 tunnels and put the entire 2 tunnels and the Nguyen Van Linh - Nguyen Huu Tho intersection into operation, serving the people on January 20.