7 major bridge and road projects in Ho Chi Minh City simultaneously open to traffic before Tet

MINH QUÂN |

HCMC - Tan Ky - Tan Quy, Ba Hom, Tang Long bridges, Hoang Hoa Tham street, Tran Quoc Hoan - Cong Hoa connecting road, Luong Dinh Cua,... will open to traffic on January 20.

On January 8, the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board) reported to the Ho Chi Minh City People's Committee on the progress of completing and opening 10 projects from now until Lunar New Year 2025.

There are 2 projects that will hold inauguration and traffic opening ceremonies, including:

Hang Bang Canal Upgrade and Renovation Project (District 5): The inauguration ceremony will take place at 8:00 a.m. on January 17, 2025.

New construction project of Tan Ky - Tan Quy bridge: Opening ceremony will be held at 8:00 a.m. on January 20, 2025.

There are 5 projects that will simultaneously open to traffic at 8:00 a.m. on January 20, 2025 (no ceremony will be held):

Project to upgrade and expand Hoang Hoa Tham Street (Tan Binh District).

Construction of the Tran Quoc Hoan – Cong Hoa connecting road: Open traffic from Phan Thuc Duyen underpass (the beginning of the route) to Hoang Hoa Tham, and simultaneously complete all 3 connection points from the route to Terminal T3 (above and below ground).

The remaining section (from Hoang Hoa Tham to the end of the route) is expected to be handed over before February 20, 2025 and completed and opened to traffic before April 30, 2025, ready to serve Terminal T3 which will come into operation on April 30, 2025.

Thi cong cau va duong noi Tran Quoc Hoan - Cong Hoa (doan qua Nha ga T3).  Anh: Minh Quan
Construction of the bridge and road connecting Tran Quoc Hoan - Cong Hoa (section through Terminal T3). Photo: Minh Quan

Project to upgrade and expand Luong Dinh Cua Street: Open to traffic from Nguyen Hoang to Tran Nao intersection. However, some areas near the intersection will continue to be under construction due to delays in site clearance.

Project to upgrade and expand Duong Quang Ham street: 1 of the entire route will be opened to traffic and phase 2 will be opened to traffic (the entire cross-section will be open to traffic) after the City Electricity Corporation completes the undergrounding and relocation of electric poles on April 30, 2025.

Duong Duong Quang Ham (quan Go Vap) duoc mo rong. Anh: Anh Tu
Duong Quang Ham Street (Go Vap District, Ho Chi Minh City) is being expanded. Photo: Anh Tu

New Tang Long Bridge construction project: One unit opened to traffic.

The new Ba Hom bridge construction project will open the entire main bridge to traffic on January 26, 2025.

At the An Phu intersection project (Thu Duc City), the Ba Dat bridge and Giong Ong To 2 bridge have both been completed but not yet put into operation. They are expected to open to traffic along with the entire An Phu intersection on December 31, 2025.

In addition, the construction project of Nguyen Van Linh - Nguyen Huu Tho intersection (District 7) will complete all work on the roofs of HC1 and HC2 tunnels and put the entire 2 tunnels and the Nguyen Van Linh - Nguyen Huu Tho intersection into operation, serving the people on January 20.

MINH QUÂN
TIN LIÊN QUAN

Trillion-dollar road surface to ease traffic jams in Go Vap

|

HCMC - The Duong Quang Ham Street expansion project (Go Vap) is speeding up construction progress, with the goal of completing the expansion to 6 lanes in 2025.

4,800 billion VND road to "rescue" Tan Son Nhat traffic jam reaches 88% of volume

|

HCMC - The Tran Quoc Hoan - Cong Hoa connecting road, costing over VND4,800 billion, has reached 88% completion, and is expected to open the entire route by the end of February 2025, reducing traffic congestion at Tan Son Nhat airport.

Ho Chi Minh City opens 9-year-old unfinished road in Thu Duc

|

HCMC - After 9 years of implementation, Luong Dinh Cua Street (from Nguyen Hoang Street to Tran Nao intersection, Thu Duc City) will open to traffic before Lunar New Year 2025.

Forest fire in Bai Chay ward, Ha Long city

|

Quang Ninh - The forest in Bai Chay ward, Ha Long city is still burning due to strong winds and dry weather.

Deputy Prime Minister inspects progress of Long Thanh airport project

|

Dong Nai - On the afternoon of January 9, Deputy Prime Minister Tran Hong Ha and a delegation of the Government and ministries worked and inspected the progress of the Long Thanh airport project.

Approving the election results of the Chairman of the People's Committee of Nghe An and Bac Giang provinces

|

On January 9, 2025, Prime Minister Pham Minh Chinh signed and issued Decisions approving the election results for the positions of Chairman of the People's Committee of Nghe An province and Chairman of the People's Committee of Bac Giang province.

Cruise missile strikes, vehicles burn in Ukraine

|

Ukraine accused Russia of using cruise missiles to attack on January 8, killing many people and setting many vehicles on fire.

It took 3 years to build more than 700m of road in Da Lat

|

Lam Dong - After many years of construction, the contractor has only built about 700m of the road to Xuan Huong Lake in Da Lat city.

Trillion-dollar road surface to ease traffic jams in Go Vap

Anh Tú |

HCMC - The Duong Quang Ham Street expansion project (Go Vap) is speeding up construction progress, with the goal of completing the expansion to 6 lanes in 2025.

4,800 billion VND road to "rescue" Tan Son Nhat traffic jam reaches 88% of volume

MINH QUÂN |

HCMC - The Tran Quoc Hoan - Cong Hoa connecting road, costing over VND4,800 billion, has reached 88% completion, and is expected to open the entire route by the end of February 2025, reducing traffic congestion at Tan Son Nhat airport.

Ho Chi Minh City opens 9-year-old unfinished road in Thu Duc

TÚ QUÂN |

HCMC - After 9 years of implementation, Luong Dinh Cua Street (from Nguyen Hoang Street to Tran Nao intersection, Thu Duc City) will open to traffic before Lunar New Year 2025.