On December 14, information from Mr. Tran Van Huyen - Executive Director of the joint venture contractor for package 21 (Lizen Joint Stock Company) said that it is expected that by the end of December 2024, the first kilometers of Bien Hoa - Vung Tau expressway will begin to be paved and efforts will be made to basically complete over 90% of the work volume by April 30, 2025, the section deployed by Lizen Joint Stock Company.
Package No. 21 of component project 1 of Bien Hoa - Vung Tau expressway passes through 5 communes and towns of Long Thanh district including An Phuoc commune, Long Duc commune, Long Thanh town, Loc An commune, Long An commune.
According to Mr. Huyen, due to the more favorable weather, the contractor has mobilized all motorbikes, equipment and workers to work in 3 shifts, 4 shifts continuously day and night to speed up the progress.
According to the Dong Nai Province Traffic Construction Project Management Board, the Bien Hoa - Vung Tau Expressway component project 1 is 16 km long through Dong Nai province, starting from National Highway 1 (Bien Hoa City) and ending at Long An Commune (Long Thanh District).
The project includes two construction packages, including package No. 18 (Km0+000 - Km6+200) through Bien Hoa City, which is implementing 6 construction phases, including Buong River bridge, roadbed, horizontal drainage culvert, residential underpass, Super T girder casting and precast components, with current output reaching about 3.2%.
Package No. 21 (Km6+200 - Km16+000) through Long Thanh district is organizing 15 construction teams, including Nuoc Trong bridge, overpass, main line bridge, roadbed, weak soil treatment, and girder casting, with output reaching about 18.1%.
Bien Hoa - Vung Tau Expressway, passing through Dong Nai and Ba Ria - Vung Tau provinces, is nearly 54 km long and will start construction in June 2023.
In Dong Nai province, component project 1 and component project 2 will be constructed, and in Ba Ria - Vung Tau province, component project 3 will be constructed.
In phase 1, the project is invested in a scale of 4-6 lanes (depending on each route section).
Total investment is more than 17,800 billion VND.