17,800 billion VND highway through Dong Nai paved at the end of December

HÀ ANH CHIẾN |

The representative of the joint venture contractor for package 21 (Lizen Joint Stock Company) said that it is expected that the Bien Hoa - Vung Tau expressway will be paved with asphalt by the end of December.

On December 14, information from Mr. Tran Van Huyen - Executive Director of the joint venture contractor for package 21 (Lizen Joint Stock Company) said that it is expected that by the end of December 2024, the first kilometers of Bien Hoa - Vung Tau expressway will begin to be paved and efforts will be made to basically complete over 90% of the work volume by April 30, 2025, the section deployed by Lizen Joint Stock Company.

Package No. 21 of component project 1 of Bien Hoa - Vung Tau expressway passes through 5 communes and towns of Long Thanh district including An Phuoc commune, Long Duc commune, Long Thanh town, Loc An commune, Long An commune.

Thi cong xuyen dem tai goi thau so 21 cao toc Bien Hoa - Vung Tau doan qua tinh Dong Nai. Anh: HAC
Construction works overnight at package 21 of Bien Hoa - Vung Tau expressway through Dong Nai province. Photo: HAC

According to Mr. Huyen, due to the more favorable weather, the contractor has mobilized all motorbikes, equipment and workers to work in 3 shifts, 4 shifts continuously day and night to speed up the progress.

According to the Dong Nai Province Traffic Construction Project Management Board, the Bien Hoa - Vung Tau Expressway component project 1 is 16 km long through Dong Nai province, starting from National Highway 1 (Bien Hoa City) and ending at Long An Commune (Long Thanh District).

The project includes two construction packages, including package No. 18 (Km0+000 - Km6+200) through Bien Hoa City, which is implementing 6 construction phases, including Buong River bridge, roadbed, horizontal drainage culvert, residential underpass, Super T girder casting and precast components, with current output reaching about 3.2%.

Package No. 21 (Km6+200 - Km16+000) through Long Thanh district is organizing 15 construction teams, including Nuoc Trong bridge, overpass, main line bridge, roadbed, weak soil treatment, and girder casting, with output reaching about 18.1%.

Bien Hoa - Vung Tau Expressway, passing through Dong Nai and Ba Ria - Vung Tau provinces, is nearly 54 km long and will start construction in June 2023.

In Dong Nai province, component project 1 and component project 2 will be constructed, and in Ba Ria - Vung Tau province, component project 3 will be constructed.

In phase 1, the project is invested in a scale of 4-6 lanes (depending on each route section).

Total investment is more than 17,800 billion VND.

HÀ ANH CHIẾN
TIN LIÊN QUAN

License to mine 1 million m3 of soil for Bien Hoa - Vung Tau expressway

|

Dong Nai - The total volume of soil exploited as filling material for the Bien Hoa - Vung Tau expressway construction in Phuoc Binh commune, Long Thanh district is nearly 1 million m3 of soil.

Adjusting the planning of the West side of Bien Hoa - Vung Tau Expressway

|

Dong Nai has locally adjusted the planning of a part of the urban area west of Bien Hoa - Vung Tau highway in Long Hung commune and Tam Phuoc ward, Bien Hoa city.

Failure to hand over sufficient land for Bien Hoa - Vung Tau expressway will result in disciplinary action

|

The Chairman of Dong Nai Provincial People's Committee proposed to reward and discipline communes and wards of Bien Hoa City and Long Thanh District for the progress of Bien Hoa - Vung Tau Expressway.

Worrying signs from TPBank's financial "health"

|

TPBank is facing major challenges in terms of operational efficiency and risk control amid increasing growth pressure.

General Phan Van Giang attends the founding ceremony of the 34th Army Corps

|

Gia Lai - The birth of the 34th Corps marked the growth of the army, ready to defeat all forms of future invasion.

No way to hide at work when violating alcohol concentration

|

Many people who violate alcohol concentration often try to hide their job or work unit.

People agree to hand over land for Metro Line 2 project

|

HCMC - Households in District 3 have agreed to hand over the land to prepare for the start of Metro Line 2 project (Ben Thanh - Tham Luong) in 2025.

Landslide leaves more than 100 tourists stranded on Khanh Le Pass

|

Khanh Hoa - Many landslides on Khanh Le Pass trapped more than 100 tourists and nearly 30 vehicles.

License to mine 1 million m3 of soil for Bien Hoa - Vung Tau expressway

HÀ ANH CHIẾN |

Dong Nai - The total volume of soil exploited as filling material for the Bien Hoa - Vung Tau expressway construction in Phuoc Binh commune, Long Thanh district is nearly 1 million m3 of soil.

Adjusting the planning of the West side of Bien Hoa - Vung Tau Expressway

HÀ ANH CHIẾN |

Dong Nai has locally adjusted the planning of a part of the urban area west of Bien Hoa - Vung Tau highway in Long Hung commune and Tam Phuoc ward, Bien Hoa city.

Failure to hand over sufficient land for Bien Hoa - Vung Tau expressway will result in disciplinary action

HÀ ANH CHIẾN |

The Chairman of Dong Nai Provincial People's Committee proposed to reward and discipline communes and wards of Bien Hoa City and Long Thanh District for the progress of Bien Hoa - Vung Tau Expressway.