Can Tho - Ca Mau Expressway accelerates to the finish line, breaking the isolation of Western traffic

Tạ Quang - Nhật Hồ |

Can Tho - At the Can Tho - Ca Mau expressway construction site, 2,100 workers and engineers are racing every hour, despite the sun and rain to catch up with the historic happy day.

Sprinting before the completion date

In early December, the working atmosphere at the project site with a total investment of more than VND 27,523 billion was always in a state of high urgency. From Can Tho gateway to Ca Mau, the 110km expressway is gradually taking shape as a "sild strip" that is being completed, ensuring the goal of completing the entire project by December 19 as directed by the Government.

Diem dau du an cao toc Can Tho - Ca Mau dang tham nhung met be tong nhua cuoi cung. Anh: Ta Quang
The starting point of the Can Tho - Ca Mau expressway project is paving the last meters of asphalt concrete. Photo: Ta Quang

Despite the erratic weather, workers are still working hard on every meter of road and bridge. Mr. Nguyen Thanh Chan - a highway construction worker - shared that he was very happy when the highway passed through the area where he lived and felt proud to contribute to the national key project.

Ong Nguyen Thanh Chan chia se khi duoc dong gop cong suc cho cong trinh trong diem quoc gia. Anh: Ta Quang
Mr. Nguyen Thanh Chan shared when he was able to contribute his efforts to a national key project. Photo: Ta Quang

When we received the information that it had to be completed by December 19, we all worked hard to make progress. That will be the common joy of all workers and people in the Western region after many years of waiting, Mr. Nguyen Thanh Chan happily said.

Mr. Dang Ngoc Minh - Executive Director of Component 1 of Can Tho - Hau Giang section (My Thuan Project Management Board) - said that Component 1 project is 37.95 km long and has basically completed over 93% of the project volume. The unit is vigorously implementing and constructing some items to install traffic safety components, ensuring the completion of the main route before December 19.

Tai nut giao IC5 cung dang duoc tham be tong nhua. Anh: Ta Quang
The IC5 intersection is also being paved with asphalt concrete. Photo: Ta Quang

My Thuan Project Management Board informed that as of December 2, the overall progress of the entire route is currently about 90%. Currently, construction units are focusing on 1,150 machines and equipment, 2,100 workers, focusing on organizing construction in 3 shifts, 4 teams with the highest determination to complete the project on schedule.

Expectations to open new development space for the Mekong Delta

Mr. Lam Van Bi - Vice Chairman of Ca Mau Provincial People's Committee - said that the major transport projects being implemented in the province are of special importance. Not only completing the strategic infrastructure system, creating a breakthrough in marine economic development, ensuring national defense and security, but also breathing new life, strengthening the trust and excitement of the people in the southernmost part of the Fatherland.

Cong tac tham be tong nhua cung dang trien khai tai dia ban tinh Ca Mau. Anh: Nhat Ho
Asphalt concrete paving is also being implemented in Ca Mau province. Photo: Nhat Ho

According to the Vice Chairman of the People's Committee of Ca Mau province, Ca Mau people expect the projects to open up new development space, enhance inter-regional connectivity, promote tourism and trade, create more jobs and maximize the existing potential and strengths of the locality.

From a business perspective, Dr. Tran Khac Tam - Chairman of the Soc Trang Business Association - said that the Can Tho - Ca Mau expressway will solve one of the biggest "bottlenecks" in the Mekong Delta. For a long time, the whole region has depended on National Highway 1 and the narrow provincial road system, causing many difficulties in transporting goods and traveling. When the expressway comes into operation, travel time between economic centers in the region will be significantly reduced; the connection from the provinces to Can Tho International Airport will also be more convenient.

Cong nhan thi cong hang muc lap dat cau kien an toan giao thong. Anh: Ta Quang
Workers constructing the installation of traffic safety components. Photo: Ta Quang

According to Dr. Tran Khac Tam, logistics and import-export businesses will benefit greatly when expressways help reduce congestion, reduce transportation interruptions - factors that increase production costs and reduce the competitiveness of goods. Reducing transportation costs will strongly support the agricultural - aquatic processing, logistics, and trade sectors, helping products of the Mekong Delta region increase their advantage in the domestic and international markets.

Tu cua ngo Can Tho den Ca Mau, 110km tuyen cao toc dan thanh hinh nhu mot “dai lua” dang duoc hoan thien. Anh: Ta Quang
From Can Tho gateway to Ca Mau, the 110km expressway is gradually taking shape like a "sild strip" that is being completed. Photo: Ta Quang

The Chairman of the Soc Trang Business Association also informed that in recent years, transport infrastructure in the Mekong Delta has received strong investment attention from the Party and the State. vertical and vertical expressways are gradually taking shape, creating great development momentum for the entire region. And the Mekong Delta is converging "time - land - prosperity" to join the country in a new stage of development.

The Can Tho - Ca Mau expressway project is 110.85km long, divided into 2 component projects: Can Tho - Hau Giang section and Hau Giang - Ca Mau section. The total investment is VND 27,523 billion, started on January 1, 2023, and is scheduled to be completed in December 2025.

Tạ Quang - Nhật Hồ
RELATED NEWS

The race of the last 15 days at the Can Tho - Ca Mau expressway construction site

|

Can Tho - In just 15 days, the Can Tho - Ca Mau expressway will officially open to traffic. The project has an investment capital of more than VND 27,500 billion, and is completing the final items.

More than 2,000 workers race overnight on the Can Tho - Ca Mau expressway project

|

Can Tho - 2,100 workers and 1,150 machines are racing to complete the 110 km expressway before the opening date of December 19, 2025

Bridge project worth over 135 billion VND in Can Tho "standing still", at risk of prolonged delays

|

Can Tho - The O Mon bridge project worth over VND135 billion is behind schedule due to land clearance problems, while the bridge is temporarily narrow, causing congestion and traffic insecurity.

Vietnam table tennis team practices with Russia

|

The players of the Vietnam Table Tennis Team were rubbed off before the 33rd SEA Games with the Russian Federation team.

Mr. Putin affirmed that Russia has no intention of returning to G8

|

President Putin affirmed that Russia has no intention of returning to the G8, and highly appreciated the strong rise of the Indian economy.

Preparing for the peak of the dry season, the Lo River begins to dry up

|

Tuyen Quang - Although not yet the peak of the dry season, many upstream areas of the Lo River have begun to dry up, exposing underground rock covers.

Another deep flooding point on National Highway 1 through Lam Dong

|

Lam Dong - Floodwaters caused deep flooding at km1700 of National Highway 1, causing traffic congestion.

The BT project of La Vong Group was once clarified for violations

|

Regarding the BT project invested by a company under La Vong Group, the Government Inspectorate has pointed out many violations.

The race of the last 15 days at the Can Tho - Ca Mau expressway construction site

Tạ Quang |

Can Tho - In just 15 days, the Can Tho - Ca Mau expressway will officially open to traffic. The project has an investment capital of more than VND 27,500 billion, and is completing the final items.

More than 2,000 workers race overnight on the Can Tho - Ca Mau expressway project

Tạ Quang |

Can Tho - 2,100 workers and 1,150 machines are racing to complete the 110 km expressway before the opening date of December 19, 2025

Bridge project worth over 135 billion VND in Can Tho "standing still", at risk of prolonged delays

Tạ Quang |

Can Tho - The O Mon bridge project worth over VND135 billion is behind schedule due to land clearance problems, while the bridge is temporarily narrow, causing congestion and traffic insecurity.