Bridge project worth over 135 billion VND in Can Tho "standing still", at risk of prolonged delays

Tạ Quang |

Can Tho - The O Mon bridge project worth over VND135 billion is behind schedule due to land clearance problems, while the bridge is temporarily narrow, causing congestion and traffic insecurity.

Speaking to Lao Dong Newspaper reporter, Mr. Nguyen Hoang Viet - Director of the CD-XL02 package Management Board (Chief Company 873 - Traffic Construction) said that the O Mon bridge project is facing the biggest difficulties in the area of pothole 12, where there are still some households that have not handed over the site, making it impossible for the construction unit to drill and fill the piles.

Du an cau O Mon (TP Can Tho) dat khoang 70% khoi luong thi cong. Anh: Ta Quang
The O Mon bridge project (Can Tho city) has reached about 70% of the construction volume. Photo: Ta Quang

According to Mr. Nguyen Hoang Viet, the entire project still has 7 households and the site handover has not been completed. It is expected that by the end of November, these cases will be enforced for handover. However, if the site is handed over immediately afterwards, mobilizing construction to speed up will not be able to help the project open to traffic before December 31 as planned.

Up to now, the project has reached about 70% of the volume, but all remaining items depend on the site clearance progress.

Mr. Nguyen Hoang Viet also said that if the bridge abutments are not completely cleared, the contractor cannot drill and fill the bridge abutments.

Du an dang gap kho khan o khau giai phong mat bang. Anh: Ta Quang
The project is facing difficulties in site clearance. Photo: Ta Quang

The contractor's representative informed that the project will generate capital due to many reasons: high sand and stone prices; two temporary routes at the beginning of demand were calculated to be used for 18 months but in reality, they have been extended much, causing maintenance and repair costs to increase sharply.

In addition, the costs are unpredictable, such as ensuring traffic due to the actual traffic volume being higher than the initial survey. Large trucks, even exceeding the load, often travel, causing the road to temporarily deteriorate rapidly, forcing continuous repairs. The total estimated capital is 15-20 billion VND.

Mr. Nguyen Hoang Viet added that after the site is cleared, the unit will focus on maximum human resources and equipment, and at the same time requested the investor to support to speed up the progress, striving to complete by April 30.

Mat cau nho hep nhung phai khai thac cung luc nhieu loai phuong tien. Anh: Ta Quang
The bridge surface is narrow but many types of vehicles must be exploited at the same time. Photo: Ta Quang

Reporters' records show that O Mon temporary bridge is experiencing many problems that directly affect traffic safety. The bridge surface is narrow but many types of vehicles must be exploited at the same time, leading to prolonged congestion at both ends of the bridge, especially during rush hour. The temporary bridge is also under great pressure, including overloaded vehicles, affecting the structure.

Notably, the bridge area is also flooded during heavy rain. The slope of the Thot Not approach bridge is often deeply flooded, causing vehicles to lose visibility, have difficulty moving and pose a potential safety risk.

Mr. Nguyen Ho Dang Khoa (O Mon ward, Can Tho city) who often travels across the temporary bridge shared that congestion has become a familiar situation every day.

According to Mr. Khoa, the large traffic volume while the bridge surface is small makes the movement slow, affecting the daily life, work and going to school of students. The continuous traffic of heavy trucks also caused vibrations, causing people to worry about the safety level of the temporary bridge.

The new O Mon Bridge was built on the old bridge location, with a total investment of more than 135 billion VND, a level III road bridge project, with a bridge surface of 12m wide, including 7 spans, 3.5m clearance. This is one of 5 bridges under the project of Raising the clearance of road bridges across the national inland waterway phase 1 (Southern area), invested by the Maritime and Waterway Project Management Board. The completion time is expected to be at the end of December 2025.

The current temporary bridge is a 7- spans iron bridge, built parallel to the old bridge to serve traffic during the construction period.

Tạ Quang
RELATED NEWS

The Ministry of Construction responds to regulations on building resettlement projects

|

The Ministry of Construction has just responded to the Quang Tri Department of Justice on the proposal to regulate the construction of a resettlement project.

Hanoi enforces land acquisition for a project of 22,875m2 next to Ring Road 2.5

|

Hanoi - The authorities of Khuong Dinh ward have organized the enforcement of a number of households that do not approve the handover of the site for the Thanh Xuan District Funeral Home project.

Resettlement projects to serve the site clearance of the VND48,800 billion road in Bac Ninh

|

Bac Ninh - The Provincial People's Committee has just issued an official dispatch introducing the location and agreeing on the locations of the resettlement area serving the site clearance of the road connecting Gia Binh airport with Hanoi city.

Nghe An nearly doubles the assigned social housing target

|

Nghe An - Nghe An province has nearly doubled the assigned targets, becoming a bright spot in the speed of implementing social housing projects.

Gold price update on the morning of November 28: High, investors waiting for the Fed's move

|

Gold price update on the morning of November 28: Steady near the highest level in two weeks. Investors assess the possibility of the Fed cutting interest rates in December.

Removing bottlenecks to help the 6,000 billion VND traffic project in the Northwest reach the finish line

|

The project to connect the traffic of the Northern mountainous provinces with a total investment of more than 6,000 billion VND, nearly 200 km long, is facing many difficulties in site clearance.

Impressive 31.5 km of Ho Chi Minh road through vast rubber gardens

|

HCMC - The 31.5 km long Ho Chi Minh road through Binh Duong province passes through vast rubber gardens, creating a rare landscape.

High waves damage 150m of sea dyke along seafood restaurants in Mui Ne

|

Lam Dong - A section of the sea dyke about 150m long through the area with a large seafood restaurant in Mui Ne was damaged by big waves.

The Ministry of Construction responds to regulations on building resettlement projects

Xuyên Đông |

The Ministry of Construction has just responded to the Quang Tri Department of Justice on the proposal to regulate the construction of a resettlement project.

Hanoi enforces land acquisition for a project of 22,875m2 next to Ring Road 2.5

SÓNG HỮU |

Hanoi - The authorities of Khuong Dinh ward have organized the enforcement of a number of households that do not approve the handover of the site for the Thanh Xuan District Funeral Home project.

Resettlement projects to serve the site clearance of the VND48,800 billion road in Bac Ninh

Vân Trường |

Bac Ninh - The Provincial People's Committee has just issued an official dispatch introducing the location and agreeing on the locations of the resettlement area serving the site clearance of the road connecting Gia Binh airport with Hanoi city.