Racing for site clearance for the Lao Cai - Hanoi - Hai Phong railway line

Nhóm PV |

Between the peak of site clearance and construction, the Lao Cai - Hanoi - Hai Phong railway line is "running" every day to keep up with the schedule.

Review dossiers, classify problems

To ensure the progress of site handover to serve the Lao Cai - Hanoi - Hai Phong railway construction investment project, the site of the Ben Qua area leveling and technical infrastructure project (Bat Xat commune, Lao Cai province) is maintaining an urgent construction schedule with 5 continuous construction bridges.

Lao Cai la diem khoi dau cua du an duong sat
Lao Cai is the starting point of the railway project. Photo: Dinh Dai

Although there are still some locations where site clearance has not been completed, the investor and contractor clearly define the motto "where there is land, construct compactly", determined not to let the overall progress of the project be affected.

On the construction site, hundreds of engineers and workers along with machinery and transportation vehicles operate continuously. The sound of machines and the bustling pace of labor throughout the holidays is like a commitment to the progress of the national key transportation project.

Nha thau chay “nuoc rut“, trien khai theo huong co mat bang den dau se thi cong gon den do.
Contractors "race" against time, deploying in the direction that where there is land, construction will be done neatly. Photo: Dinh Dai

According to Major Le Thanh Dat - Site Commander, Truong Son Construction Corporation is currently maintaining more than 100 engineers and workers along with dozens of equipment and vehicles, organizing 5 construction teams, including 2 teams for excavating and filling ground, connecting roads and 3 teams for casting components.

The weather is favorable for construction. If the locality hands over more land, we are ready to increase manpower, equipment, and expand the construction wing to speed up progress," Major Le Thanh Dat said.

To date, the project has been handed over about 10ha/75ha of total area. For the area that has land, the construction volume has reached about 95%.

Ban do huong tuyen duong sat Lao Cai - Ha Noi - Hai Phong. Anh: Dinh Dai
Map of the Lao Cai - Hanoi - Hai Phong railway route. Photo: Dinh Dai

To remove bottlenecks, Bat Xat commune is implementing a peak period of "40 days and nights of site clearance" (from December 22, 2025 to January 30, 2026).

The focus is on reviewing dossiers, classifying problems, strengthening dialogue with the people, completing the steps of appraisal, approval and compensation payment, ensuring publicity, transparency and the legitimate rights of the people.

Hien don vi thi cong da duoc chu dau tu va chinh quyen dia phuong ban giao 10 ha/75 ha tong dien tich mat bang du an
Currently, the construction unit has been handed over 10 ha/75 ha of the total project site area by the investor and local authorities.

Mr. Nguyen Viet Tien - Deputy Director of the Bat Xat area Construction Investment Project Management Board said that the biggest difficulty currently is handling cases related to inheritance and recovering 5% of land area managed by communes in the past. These obstacles relate to 112 households, accounting for about half of the clearance area of resettlement areas.

We are coordinating with relevant units to organize meetings to review and clarify each case, ensuring the rights of people in accordance with regulations," Mr. Tien said.

Synchronous implementation of solutions

Not only in Lao Cai, site clearance for the Lao Cai - Hanoi - Hai Phong railway line in Phu Tho province is also being drastically implemented.

Du an duong sat Lao Cai - Ha Noi - Hai Phong qua Phu Tho du kien thu hoi hon 630ha dat, anh huong den tren 1.800 ho dan phai tai dinh cu.
The Lao Cai - Hanoi - Hai Phong railway project through Phu Tho is expected to recover more than 630ha of land, affecting over 1,800 households that must be resettled. Photo: Duy Dung

An important milestone was recorded on December 19, 2025, the Phu Tho station building and square project officially started under the direction of the Prime Minister, with a total investment of 3,347 billion VND.

According to the design, the railway section through Phu Tho is about 95.1km long, passing through 20 communes and wards, arranging 7 types of stations. The project is expected to recover over 630ha of land, affecting more than 1,800 households, and at the same time must build 38 new resettlement areas, relocate nearly 5 people's cemeteries and many technical and social infrastructure projects.

Doan qua tinh Phu Tho dai khoang 99,1km, di qua 20 xa, phuong, voi diem dau tai xa Dan Thuong va diem cuoi tai phuong Phuc Yen
The section through Phu Tho province is about 95.1km long, passing through 20 communes and wards, with the starting point in Dan Thuong commune and the ending point in Phuc Yen ward. Photo: Duy Dung

Mr. Le Minh Quang - Deputy Director of Phu Tho Regional Land Development Center Branch said that the section passing through Phong Chau ward alone is more than 6.7km long, the recovered area is over 22ha, and the volume of site clearance is very large.

We have strengthened coordination with local authorities, synchronously deploying solutions to hand over land on schedule," Mr. Quang informed.

Tinh Phu Tho bo tri 5 nha ga hon hop, 1 ga hanh khach va 1 ga tac nghiep ky thuat.
Phu Tho province arranges 5 mixed terminals, 1 passenger terminal and 1 technical operation terminal. Photo: Duy Dung

Currently, the project management boards have completed 100% of the measurement work, identified 38 locations of resettlement areas and 5 expanded cemeteries, and completed compensation, support and overall resettlement plans in the area.

At a recent field inspection, Minister of Construction Tran Hong Minh emphasized that the Lao Cai - Hanoi - Hai Phong railway line is a key national transport project, in which the section through Lao Cai and Phu Tho plays the role of "first link", activating the entire logistics chain of the project.

If site clearance is slow, the entire route will be slower. It is necessary to do both site clearance and resettlement in parallel so that people can soon stabilize their lives," Minister Tran Hong Minh emphasized.

Nhóm PV
RELATED NEWS

Starting construction of 16 Lao Cai - Hanoi - Hai Phong railway stations in the first quarter of 2026

|

The remaining 16 stations of the Lao Cai - Hanoi - Hai Phong railway line are being surveyed and designed to start construction in the first quarter of 2026.

Concentrating on the Lao Cai - Hanoi - Hai Phong railway project

|

With a length of more than 143km passing through the area, Lao Cai is rapidly clearing land to serve the Lao Cai - Hanoi - Hai Phong railway project and building resettlement areas to relocate people.

More than 2,000 workers race overnight on the Can Tho - Ca Mau expressway project

|

Can Tho - 2,100 workers and 1,150 machines are racing to complete the 110 km expressway before the opening date of December 19, 2025

Prenn Pass road closed in Da Lat for 6 days to repair landslide site

|

Lam Dong - Functional agencies decided to close Prenn Pass road for 6 days to repair and fix damaged points caused by previous landslides.

Forecast of the time to end widespread severe cold in the North

|

According to a representative of the meteorological agency, it is forecast that widespread severe cold and frost in the North will last until about January 10, to prevent frost and frost in mountainous areas.

Ho Chi Minh City launches campaign to handle sidewalk and roadway encroachment throughout the area

|

Ho Chi Minh City is deploying a peak period of inspection and handling of sidewalk and roadway encroachment throughout the area to restore urban order.

A restaurant yacht catches fire on the Saigon River

|

Ho Chi Minh City - Restaurant yacht on Saigon River suddenly catches fire, functional forces are controlling the fire.

Starting construction of 16 Lao Cai - Hanoi - Hai Phong railway stations in the first quarter of 2026

PHẠM ĐÔNG |

The remaining 16 stations of the Lao Cai - Hanoi - Hai Phong railway line are being surveyed and designed to start construction in the first quarter of 2026.

Concentrating on the Lao Cai - Hanoi - Hai Phong railway project

Duy Dũng |

With a length of more than 143km passing through the area, Lao Cai is rapidly clearing land to serve the Lao Cai - Hanoi - Hai Phong railway project and building resettlement areas to relocate people.

More than 2,000 workers race overnight on the Can Tho - Ca Mau expressway project

Tạ Quang |

Can Tho - 2,100 workers and 1,150 machines are racing to complete the 110 km expressway before the opening date of December 19, 2025