Water supply project for 3,300 hectares of crops is in disarray after many years of construction

Hưng Thơ |

After many years of implementation, the Ba Ho - Ban Chua Irrigation System Project (Quang Tri province) has not been completed synchronously, many items are unfinished or do not meet the conditions for handover, causing frustration and concerns about the efficiency of using public investment resources.

Many items are not completed, functions are not promoted

According to the report of the Quang Tri Provincial Investment and Construction Project Management Board, the above project was started in 2018 with a total investment of more than 262 billion VND. The goal is to provide irrigation water for nearly 3,300 hectares of crops, serve daily life, improve the ecological environment and aquaculture. After many years of implementation, the project still has a series of problems with site clearance, design adjustments and acceptance procedures.

The entire project has 24 works, but only 18 works have been approved for handover or basic completion. The two projects are still completing documents for acceptance inspection after July 1, 2025.

Notably, 4 projects have not been handed over due to not yet completed site clearance, not enough capital allocation and design adjustments during the implementation process. For example, the embankment protecting Vinh Dai pumping station, Dau Binh pumping station, the construction road combined with management and the road to restore the lake bed of Ban Chua 1 dam... Some works have been administratively sanctioned by competent authorities for violating the approved construction design, changing the status but have not yet completed the adjustment procedures.

Request to completely handle, avoid wasting investment capital

According to the Department of Agriculture and Environment, adjusting the scale of some items will reduce irrigation areas for production, directly affecting the original target.

Typically, the Ban Chua 1 Dam project had to cut nearly 1km of the final pipeline due to no longer having capital to clear the site and land disputes, while the My Hoa pumping station reduced the main pipeline, branch pipes and rainwater spraying irrigation lines. The locality has repeatedly recommended increasing local budget capital to complete the low-voltage power item, avoiding wasting invested infrastructure.

However, the Project Management Board affirmed that the adjusted works have been constructed basically to ensure technical requirements and have been independently inspected, have the effect of preventing floods, serving people's lives in the project area. The construction value decreased by more than 390 million VND compared to the estimate, saving about 2.3 billion VND in compensation and support costs for site clearance, not exceeding the total approved investment. The unit also committed to raising the warranty period for completed items from 1 year to 2 years, raising the total warranty period to 5.5 years to ensure the quality and responsibility of the project.

On June 28, the People's Committee of Quang Tri province issued a document requesting relevant departments, branches and the Project Management Board to urgently coordinate to completely handle the problems. The Department of Construction is assigned to preside over the appraisal and adjustment of feasibility study reports and implementation designs after basic designs for constructed works with changes compared to approved designs. The Department of Agriculture and Environment continues to review and synthesize the remaining contents, reporting to the Provincial People's Committee for consideration and approval of project dossier adjustments. At the same time, the Provincial People's Committee allowed the extension of the project implementation period and related contracts until December 31, 2025 to have a basis to complete the procedures and put the entire project into use.

Faced with the situation of not being able to complete for many years, the leaders of Quang Tri province emphasized the requirement for relevant agencies and units to strictly handle violations, speed up the progress of appraisal and approval, ensure maximum use of the completed volume, and avoid wasting State capital.

Hưng Thơ
TIN LIÊN QUAN

Thai Nguyen takes strong measures to remove suspended projects

|

Many projects "holding golden land" that have not been implemented for decades, left abandoned in the heart of the city, have been strongly reclaimed by Thai Nguyen province, in order to prevent waste of resources and restore order in investment management.

Lam Dong reclaims more than 90 hectares of land to serve the Bao Loc - Lien Khuong expressway project

|

Lam Dong - Bao Loc City People's Committee and Bao Lam District People's Committee have issued notices to reclaim more than 90 hectares of land to serve the Bao Loc - Lien Khuong Expressway project.

Veterinary staff who left wrong impressions on the case of C.P were reviewed and transferred to work

|

The Department of Animal Husbandry and Veterinary Medicine has provided additional information on handling violations related to the noise of CP Vietnam Company.

Storm Mun near the Philippines rapidly intensifies, low pressure approaches the East Sea

|

Typhoon Mun near the Philippines suddenly accelerated strongly, the eye of the storm gradually appeared in the dry air mass, while another low pressure was approaching the East Sea.

Gold price update on the morning of July 3: Reversal to recover

|

Gold price update on the morning of July 3: World gold reversed and recovered strongly last night.

The job market is constantly fluctuating, choosing a major needs to be alert

|

Choosing a wise major today will be a solid foundation for your future career journey.

Phu Tho residents are busy changing signs and updating new addresses

|

Phu Tho - In early July, people in the newly merged wards from Hoa Binh to Phu Tho began to change their signs, update their documents and new addresses.

The prolonged disappointment of many business owners who have been accused of collecting social insurance

|

Many businesses that have been wrongly collected for social insurance hope to have their legitimate rights resolved after July 1, but it seems that the disappointment continues.

Thai Nguyen takes strong measures to remove suspended projects

Ngọc Minh |

Many projects "holding golden land" that have not been implemented for decades, left abandoned in the heart of the city, have been strongly reclaimed by Thai Nguyen province, in order to prevent waste of resources and restore order in investment management.

Lam Dong reclaims more than 90 hectares of land to serve the Bao Loc - Lien Khuong expressway project

Lam Hồng |

Lam Dong - Bao Loc City People's Committee and Bao Lam District People's Committee have issued notices to reclaim more than 90 hectares of land to serve the Bao Loc - Lien Khuong Expressway project.