Dong Hoi railway overpass project restarted

CÔNG SÁNG |

After a period of land clearance problems, the Dong Hoi Railway Overpass Project has resumed construction, expected to be fully completed in 2025.

Removing site obstacles

The Dong Hoi city central railway road and overpass project is 1.15km long, starting in 2022, with completion expected by the end of 2025. The project has 2 packages including a bridge construction package (contract value of more than 85 billion VND) and a road construction package (more than 13.4 billion VND).

According to Lao Dong Newspaper in late July, at the project site, construction units have resumed implementation after a period of suspension of bored pile drilling activities to construct the M1 pillar abutment. The restart took place right after the site for part of the project had just been handed over.

According to Mr. Le Tuan Loi - Head of the Economic - Infrastructure and Urban Affairs Department of Dong Thuan Ward (Quang Tri Province) - up to now, the locality has approved and paid compensation in the 5th phase to 6 households at the foot of the bridge (4 resettlement households, 1 household compensated by land, 1 household adjusting specific land prices) and 3 organizations. In the fourth phase, a household subject to resettlement has handed over the site.

However, there are still 3 households at the foot of the bridge that have not agreed on a compensation and support plan. The Ward People's Committee is continuing to dialogue and persuade households to complete the procedures soon. In particular, along Nguyen Cong Hoan Street, 24 households have announced land reclamation and are being counted for assets; the remaining 48 households are waiting to verify the origin and time of land use to issue a reclamation notice.

Speed up construction progress

Mr. Nguyen Ngoc Quy - Director of the Traffic Construction Investment Project Management Board (Quang Tri Department of Construction) - said that the project was approved by the People's Committee of Quang Binh province (old) in Decision No. 4292/QD-UBND dated December 24, 2021 and adjusted in Decision 76/QD-UBND dated January 13, 2023. In total, the project affects 97 cases, including 91 households and 6 organizations in 2 wards: Dong Hoi and Dong Thuan.

In Dong Hoi ward, 12/13 cases have been paid, reaching more than 91%. Another organization (related to the fenced assets of the Vietnam - Cuba Dong Hoi Friendship Hospital and the liquidated collective house) is counting assets.

Regarding the construction progress, the contractor has completed the M2 abutment, T2 pillar and cast 38/45 railway overpass girder films. Currently, the M1 abutment is under construction and is preparing to deploy the T1 helmet bar. For the road section, the vertical drainage system is basically completed; the contractor is implementing a cross-drainage system in areas without land clearance problems.

The Project Management Board is closely coordinating with the People's Committees of Dong Hoi and Dong Thuan wards to resolve existing problems, especially on Nguyen Cong Hoan Street. If the site clearance work is completed in August 2025, the investor will focus its efforts and speed up the progress to complete the entire project in 2025.

CÔNG SÁNG
RELATED NEWS

Removing land obstacles and resettlement for the Dong Hoi railway overpass project

|

Quang Binh - Dong Hoi City is making efforts to handle long-term problems at the Central Railway Overpass Project to speed up the progress of site clearance.

Unblocking the site for the Dong Hoi City railway overpass project

|

Quang Binh - The road and overpass project of the central railway in Dong Hoi City has been stalled due to land clearance problems, and the government is making efforts to resolve them to restart them.

Dong Hoi City railway road and overpass project stalled due to land clearance

|

The road and overpass project of the central railway of Dong Hoi city (Quang Binh province) although started in October 2022, has been stalled due to land clearance problems. Currently, there are no signs of resuming construction at the site, causing concerns about the project's progress.

It is expected to submit to the Politburo a project to reorganize and streamline mass associations before August 31

|

On the afternoon of July 29, the Central Committee of the Vietnam Fatherland Front held a conference to give comments on the project to reorganize and streamline mass associations assigned by the Party and the State.

Live football U23 Vietnam vs U23 Indonesia in the U23 Southeast Asian final

|

Live match between U23 Vietnam vs U23 Indonesia in the 2025 U23 Southeast Asian Cup final, taking place at 8:00 p.m. today (July 29).

EVN's consolidated revenue in 2024 will reach VND 580,537 billion

|

EVN has just released a consolidated financial report that has been audited in 2024. After many years of losses, EVN's financial situation has had positive results.

Khanh Hoa requests clarification of the responsibility for requesting the arrangement of a public housing at Bao Dai mansion

|

Khanh Hoa - The authorities have the results of the inspection and handling of the case, proposing to temporarily arrange accommodation for officials at the Cau Da villa relic site - where Bao Dai tower is located.

High sales caused stocks to lose the 1,500-point mark

|

Many investors have fallen into a state of anxiety and participated in strong selling when the stock market fell sharply to below the threshold of 1,500 points.

Removing land obstacles and resettlement for the Dong Hoi railway overpass project

CÔNG SÁNG |

Quang Binh - Dong Hoi City is making efforts to handle long-term problems at the Central Railway Overpass Project to speed up the progress of site clearance.

Unblocking the site for the Dong Hoi City railway overpass project

CÔNG SÁNG |

Quang Binh - The road and overpass project of the central railway in Dong Hoi City has been stalled due to land clearance problems, and the government is making efforts to resolve them to restart them.

Dong Hoi City railway road and overpass project stalled due to land clearance

CÔNG SÁNG |

The road and overpass project of the central railway of Dong Hoi city (Quang Binh province) although started in October 2022, has been stalled due to land clearance problems. Currently, there are no signs of resuming construction at the site, causing concerns about the project's progress.