slow disbursement of expressway capital due to land clearance problems and lack of construction materials

PHƯƠNG ANH |

Can Tho - 3 Component projects of the Chau Doc - Can Tho - Soc Trang Expressway Project have so far disbursed 22.1%.

According to the Department of Finance of Can Tho City, the city is currently the managing agency of 3 component projects of the Chau Doc - Can Tho - Soc Trang Expressway Construction Investment Project Phase 1, with a total central budget allocated in 2025 of about 7,040 billion VND.

As of the end of June, the disbursement value reached about VND 1,560 billion, equivalent to 22%, lower than the city average. It is estimated that the amount of capital that cannot be disbursed in 2025 is about 2,700 billion VND.

Cong nhan thi cong phan cau thuoc Du an thanh phan 4, cao toc Chau Doc - Can Tho - Soc Trang. Anh: Phuong Anh
Workers constructing the bridge part of Component Project 4, Chau Doc - Can Tho - Soc Trang Expressway. Photo: Phuong Anh

Of which, Component Project 2 with Can Tho City (old) as the managing agency has disbursed about 453/1,117 billion VND, reaching about 40.54%. The project is currently facing difficulties in the supply of raw materials, especially sand and stone. In addition, there are 3 locations of the 220kV high-voltage power line in Thanh Phu, Dong Hiep and Truong Xuan communes that have not been relocated, affecting the construction progress.

Component project 3 is managed by Hau Giang province (old) with a disbursement of about 278/2,533 billion VND, reaching 10.96%. The slow disbursement is mainly due to the lack of sand resources to meet requirements, in which sand from Ben Tre province (old) is mixed with a lot of mud, having to go through many stages of treatment, slowing down the construction process and incurring costs. Some expenses such as construction, site clearance, consulting and other expenses have decreased by about VND1,260 billion, the capital that is not likely to be disbursed this year is about VND1,500 billion.

Component project 4 managed by Soc Trang province (old) has disbursed about 825/3,389 billion VND, reaching 24.34%. This project is also lacking sand for embankment. According to estimates, about 1,200 billion VND will be difficult to fully disburse this year.

In that situation, the Department of Finance of Can Tho City is coordinating with investors to review and propose internal changes to the capital plan. In case there is still capital that cannot be disbursed after the transfer, the Department will report to the City People's Committee to submit to the Ministry of Finance and the Prime Minister for consideration of transferring to ministries, branches or localities in need in August 2025.

PHƯƠNG ANH
TIN LIÊN QUAN

Dong Thap proposes to add 350 billion VND to Cao Lanh - An Huu Expressway

|

Dong Thap - The Provincial People's Committee proposed to soon add 350 billion VND from the central budget in 2025 to Component Project 1 of the Cao Lanh - An Huu Expressway.

The shape of the rest stop on the tens of thousands of billion VND expressway in the border area is revealed

|

The expected shape of the rest stop on the Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway is revealed.

Investing in the complete construction of CT.07 expressway under the BOT form

|

The project to invest in the complete construction of the CT.07 expressway, Hanoi - Thai Nguyen - Cho Moi section, with a length of more than 100km under the form of a BOT contract.

Hanoi leaders talk about the roadmap to convert gasoline vehicles to electric vehicles

|

Hanoi will support the conversion of gasoline-powered vehicles to green fuel, applied first to people in Ring Road 1 and expanded in Ring Road 2.

The billiards community mourns Chang Jun-lin's sudden passing

|

The international billiards community was moved to commemorate player Chang Jung-lin, who recently passed away in Jakarta while participating in the 2025 PBC Indonesia tournament.

Super-small neighborhood in the heart of Ho Chi Minh City has a fire fighting system, people are still not assured

|

HCMC - Although the micro-neighborhood in the middle of HCMC has been installed with a fire fighting system by the locality, people are still worried about the risk of fire and explosion, so they open additional escape routes themselves.

Dead pigs dumped on the streets of Hanoi, Ministry of Agriculture and Environment speaks out

|

The Deputy Minister of Agriculture and Environment requested to resolutely prevent the situation of throwing dead pigs onto the road, causing the spread of the epidemic.

Top 10 localities with the most scores in 10 Math subjects, Hanoi leads

|

In the 2025 high school graduation exam, Hanoi is the leading locality in the country in terms of 10 points in Math.

Dong Thap proposes to add 350 billion VND to Cao Lanh - An Huu Expressway

Phong Linh |

Dong Thap - The Provincial People's Committee proposed to soon add 350 billion VND from the central budget in 2025 to Component Project 1 of the Cao Lanh - An Huu Expressway.

The shape of the rest stop on the tens of thousands of billion VND expressway in the border area is revealed

Khánh Linh |

The expected shape of the rest stop on the Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway is revealed.

Investing in the complete construction of CT.07 expressway under the BOT form

Việt Bắc |

The project to invest in the complete construction of the CT.07 expressway, Hanoi - Thai Nguyen - Cho Moi section, with a length of more than 100km under the form of a BOT contract.