Chuong My Ward People's Committee (Hanoi) has just organized a Conference to deploy land acquisition and site clearance for the Project to Renovate and Upgrade National Highway 6, Ba La - Xuan Mai section in the ward for households and individuals with land located within the site clearance boundary of Phuong Bai residential group (left side of the Ba La - Xuan Mai direction).
Speaking at the conference, Mr. Trinh Duy Oai - Chairman of the Ward People's Committee thoroughly grasped the purpose, requirements and content of implementing land acquisition and site clearance according to the 2024 Land Law and Decision No. 969/QD-UBND dated August 13, 2022 of the Hanoi City People's Committee.
Mr. Oai emphasized that the Project to Renovate and Upgrade National Highway 6, Ba La - Xuan Mai section is a key traffic project belonging to the radial road connecting Hanoi Capital with the Northwest provinces, which is particularly important for completing transport infrastructure, promoting socio-economic development, ensuring social security and urban aesthetics in the ward, as well as Hanoi Capital.
At the conference, households with recovered land expressed their opinions, focusing on contents such as: Red line boundary, compensation unit price, remaining land area after recovery, conditions and resettlement area,...
Answering people's opinions, Mr. Le Minh Khoi - Deputy Head of the Site Clearance Department, Hanoi Traffic Construction Investment Project Management Board said: The site clearance boundary of the Project has been agreed upon by the Hanoi City People's Committee to remain unchanged according to the plan issued from 2014; compensation and support work is carried out in accordance with the unit price decisions of the City People's Committee.
Regarding resettlement, the consideration will be based on the origin, land use process and specific investigation and verification results of each household to develop appropriate compensation, support, and resettlement plans in accordance with legal regulations.

Concluding the conference, Mr. Trinh Duy Oai - Chairman of Chuong My Ward People's Committee acknowledged, received and answered people's opinions under the authority of the locality; and at the same time requested households with recovered land to continue to study and carefully understand current regulations on compensation, support, and resettlement; strictly comply with the Party's guidelines and the State's policies and laws in the process of project implementation.
The Ward People's Committee requests households to coordinate in providing complete and truthful dossiers and related documents to serve the inventory and compensation plan; any remaining problems can be directly contacted by the Hanoi Traffic Construction Investment Project Management Board or the Ward Economic, Infrastructure and Urban Department for timely and satisfactory guidance and answers.

National Highway 6 is a vital axis, connecting Hanoi with Hoa Binh (now Phu Tho) and the Northwest provinces. In fact, National Highway 6 through Hanoi has deteriorated and been overloaded for many years, often causing congestion and traffic accidents.
To solve the above situation, at the end of 2022, the Hanoi People's Committee started the National Highway 6 expansion project, the Ba La - Xuan Mai section, with a length of about 21.7 km.
The starting point of the project is located at km14 in Ba La district, Ha Dong district (now Yen Nghia ward); the ending point is km38, Xuan Mai town, Chuong My district (now Xuan Mai commune).
The project has 5 construction packages, including items: Synchronous construction of road surface foundation, water supply and drainage, technical cable ditches, lighting, green trees, 8 road bridges, 1 newly built box culvert.
The project has a total investment of over 9,590 billion VND, implemented in the period 2022-2027.