Deputy Prime Minister Tran Hong Ha inspects two highways through Hau Giang

Tạ Quang |

Hau Giang - On the morning of November 20, Deputy Prime Minister Tran Hong Ha inspected the Can Tho - Ca Mau expressway and the Chau Doc - Can Tho - Soc Trang expressway at IC4 intersection.

Bao cao voi Pho Thu tuong va doan cong tac, ong Mai Van Tan – Giam doc So GTVT tinh Hau Giang (chu dau tu Du an thanh phan 3) cho biet, du an dai gan 37km duoc chia thanh 2 goi thau xay lap, den nay tien do dat 26%.
Reporting to the Deputy Prime Minister and the working delegation, Mr. Mai Van Tan - Director of the Department of Transport of Hau Giang province (investor of Component Project 3) - said that the nearly 37km long project is divided into 2 construction packages, and the progress has reached 26% so far.
Du an co 3 nut giao, 24 cau, cong tac giai phong mat bang da dat 100%.
The project has 3 intersections, 24 bridges, and site clearance has reached 100%.
Ve vat lieu, nhu cau du an can khoang 6 trieu m3. Trong do, duoc cap nguon o An Giang 2,6 trieu m3 (vua qua da chia se cho du an Can Tho – Ca Mau khoang 500 nghin m3).
Regarding materials, the project needs about 6 million m3. Of which, 2.6 million m3 is supplied from An Giang (recently shared with the Can Tho - Ca Mau project about 500 thousand m3).
Doi voi cao toc Can Tho – Ca Mau, ong Le Duc Tuan - Pho Giam doc BQL du an My Thuan cho hay, tinh hinh trien khai thi cong, den nay da thuc hien xong khoang 50% khoi luong hop dong.
Regarding the implementation of the Can Tho - Ca Mau expressway project, Mr. Le Duc Tuan - Deputy Director of the My Thuan Project Management Board - said that up to now, about 50% of the contract volume has been completed.
Du an chi con khoang 200m tuyen noi nam tren dia ban TP Can Tho vuong bai rac, du kien trong thang 12.2024, dia phuong se hoan thanh viec di doi.
The project has only about 200m of connecting route located in Can Tho city, stuck with landfill, and it is expected that in December 2024, the locality will complete the relocation.
Ong Le Duc Tuan thong tin them, kho khan, vuong mac lon nhat hien nay cua du an van la vat lieu. Den nay, cac tinh An Giang, Dong Thap, Vinh Long da cap cho du an khoang 19 trieu m3 cat, co ban ve tru luong la du, nhung cong suat khai thac thi hien dang thieu.
Mr. Le Duc Tuan added that the biggest difficulty and obstacle of the project is still materials. Up to now, An Giang, Dong Thap and Vinh Long provinces have provided the project with about 19 million m3 of sand. The reserves are basically sufficient, but the exploitation capacity is currently lacking.
Tai cong truong, Pho Thu tuong Tran Hong Ha yeu cau chieu nay lam viec tai tinh Soc Trang, cac chu dau tu, dia phuong, bao cao chi tiet, cu the ve cac van de kho khan, vuong mac, de xuat, kien nghi thao go de day nhanh tien do cac du an.
At the construction site, Deputy Prime Minister Tran Hong Ha requested that this afternoon, working in Soc Trang province, investors and localities, report in detail and specifically on difficulties and problems, propose and recommend solutions to speed up the progress of projects.
Pho Thu tuong Tran Hong Ha cung luu y, xay dung duong cao toc phai dam bao yeu to dac thu cua vung song nuoc mien Tay, khong can tro ve dong chay, nguon nuoc anh huong den san xuat, sinh hoat cua nguoi dan…
Deputy Prime Minister Tran Hong Ha also noted that the construction of the expressway must ensure the specific characteristics of the Mekong Delta river region, not hindering the flow or water sources that affect production and people's lives...
Tạ Quang
TIN LIÊN QUAN

The landfill blocking the Can Tho - Ca Mau highway is about to be relocated

|

Can Tho - Construction is expected to start on November 15 to relocate the landfill blocking the Can Tho - Ca Mau highway.

More than 13 billion VND to relocate the landfill blocking the Can Tho - Ca Mau highway

|

Can Tho - The cost of relocating the landfill blocking the Can Tho - Ca Mau expressway is 13.08 billion VND and will complete handover of 100% of the site before December 31.

Increasing sand exploitation capacity for Can Tho - Ca Mau highway

|

Deputy Minister of Transport Nguyen Duy Lam requested contractors to increase maximum exploitation capacity, add more dredgers and barges to transport sea sand for the expressway project.

Miss Thanh Thuy: Salary is not the biggest value

|

Miss Huynh Thi Thanh Thuy had a conversation with Lao Dong reporter about her journey to conquer the crown.

Teachers have the right to teach extra lessons as a legitimate activity

|

National Assembly delegates agreed with the regulation that teachers have the right to teach extra classes as a legitimization for this legitimate activity.

Case of 5 missing students in Phu Tho: 3 remaining bodies found

|

Phu Tho - By the morning of November 20, authorities had found the remaining three bodies in the case of five 8th grade students drowning and going missing on the Red River.

Series of former officials on trial for assisting Xuyen Viet Oil

|

HCMC - Covering up violations for Xuyen Viet Oil, former Secretary of Ben Tre Provincial Party Committee, former Deputy Minister of Industry and Trade and 13 other defendants had to appear in court this morning.

The 1,500 billion VND project to expand the gateway to Ho Chi Minh City is "stuck" because of 8 houses

|

HCMC - The 1,500 billion VND National Highway 50 expansion project has been stalled because 8 houses have not been cleared, causing the parallel road to be interrupted even though it is 75% complete.

The landfill blocking the Can Tho - Ca Mau highway is about to be relocated

Tạ Quang |

Can Tho - Construction is expected to start on November 15 to relocate the landfill blocking the Can Tho - Ca Mau highway.

More than 13 billion VND to relocate the landfill blocking the Can Tho - Ca Mau highway

Tạ Quang |

Can Tho - The cost of relocating the landfill blocking the Can Tho - Ca Mau expressway is 13.08 billion VND and will complete handover of 100% of the site before December 31.

Increasing sand exploitation capacity for Can Tho - Ca Mau highway

Tạ Quang |

Deputy Minister of Transport Nguyen Duy Lam requested contractors to increase maximum exploitation capacity, add more dredgers and barges to transport sea sand for the expressway project.