Deputy Prime Minister inspects highway construction site in Ha Tinh

TRẦN TUẤN |

Ha Tinh - On March 9, the Government inspection team No. 2, led by Deputy Prime Minister Nguyen Chi Dung, inspected the expressway construction site in Ha Tinh.

The working group inspected 3 component projects of the North - South expressway in the East phase 2021 - 2025 in Ha Tinh, including: Bai Vot - Ham Nghi; Ham Nghi - Vung Ang; Vung Ang - Bung.

According to the report of the Thang Long Project Management Board (investor of Bai Vot - Ham Nghi and Ham Nghi - Vung Ang Expressway), after more than 2 years of construction, the output of the Bai Vot - Ham Nghi Expressway section (more than 35km long) has reached 80% of the contract value, the Ham Nghi - Vung Ang section (more than 53km long) has reached 84.2% of the contract value, ensuring the set plan.

Project Management Board 6 (investor of Vung Ang - Bung expressway) said that the Vung Ang - Bung expressway section is 55.34km long, of which the section through Ha Tinh is 12.9km long with main items including: Deo But tunnel, main route and 5 basic bridges meeting the schedule.

Representatives of investors informed that currently, the construction of the North-South expressway through Ha Tinh does not have any difficulties or problems with land and construction materials. However, in recent times, the weather has had a lot of rain, making construction somewhat difficult.

Investors and contractors are committed to making the highest efforts to speed up the progress to basically complete the main route through Ha Tinh by April 30, opening the entire route from Ha Tinh to Quang Tri on June 30 under the direction of the Government.

Doan cong tac Chinh phu kiem tra cao toc o Ha Tinh. Anh: Quang Tien.
The Government working group inspected the expressway in Ha Tinh. Photo: Quang Tien

Deputy Prime Minister Nguyen Chi Dung acknowledged and highly appreciated the efforts of local authorities in site clearance, investors and contractors in ensuring construction progress.

Deputy Prime Minister Nguyen Chi Dung emphasized that there is not much time left from now until June 30. Therefore, units must focus with the highest and fastest spirit to complete the goal of opening the main route of the North - South expressway in the East phase 2021 - 2025 from Ha Tinh to Quang Tri.

Pho Thu tuong Nguyen Chi Dung tang qua cho don vi thi cong tren cong truong. Anh: Quang Tien.
Deputy Prime Minister Nguyen Chi Dung presented gifts to the construction unit at the construction site. Photo: Quang Tien

On this occasion, the working group presented gifts to encourage contractors and construction workers at the construction site.

TRẦN TUẤN
TIN LIÊN QUAN

Quang Tri proposes to add a residential access road on the expressway

|

Quang Tri - Some sections of the residential road on the Van Ninh - Cam Lo expressway have not been invested in construction, affecting people's travel.

HCMC builds 2 major intersections connecting Ben Luc - Long Thanh Expressway

|

HCMC - The two intersections connecting Ben Luc - Long Thanh Expressway with Rung Sac Road and National Highway 50 will be approved for investment in the second quarter of 2025, starting construction in 2026.

Tuyen Quang proposes to add VND 7,237 billion to expressway project

|

Tuyen Quang province proposed that the Government provide additional support of VND 7,237 billion to complete both phases of the Tuyen Quang - Ha Giang expressway project.

Mercedes driver hits a series of vehicles waiting for red lights when having alcohol concentration

|

HCMC - On the evening of March 16, the authorities determined that the female Mercedes driver who caused the series of accidents at Thu Duc intersection had alcohol concentration on her body.

pine forest fire under Da Lat cable car, black smoke

|

Lam Dong - A major forest fire occurred in the pine forest area under the cable car route in Da Lat. Black smoke rose high and spread, causing suffocation and difficulty breathing for people.

Live football Arsenal 1-0 Chelsea: Second half

|

Live match between Arsenal vs Chelsea in round 29 of the Premier League takes place at 20:30 on March 16.

Coming to Hanoi is no longer a nightmare for international tourists

|

Hanoi - Thanks to improved infrastructure and traffic awareness, international tourists can now clearly feel the change when traveling on Hanoi streets.

5-storey hotel fire in Ho Chi Minh City, 6 people escaped

|

HCMC - A hotel in Thu Duc City suddenly caught fire, 6 people inside were fortunately rescued by firefighters.

Quang Tri proposes to add a residential access road on the expressway

HƯNG THƠ |

Quang Tri - Some sections of the residential road on the Van Ninh - Cam Lo expressway have not been invested in construction, affecting people's travel.

HCMC builds 2 major intersections connecting Ben Luc - Long Thanh Expressway

MINH QUÂN |

HCMC - The two intersections connecting Ben Luc - Long Thanh Expressway with Rung Sac Road and National Highway 50 will be approved for investment in the second quarter of 2025, starting construction in 2026.

Tuyen Quang proposes to add VND 7,237 billion to expressway project

Việt Bắc |

Tuyen Quang province proposed that the Government provide additional support of VND 7,237 billion to complete both phases of the Tuyen Quang - Ha Giang expressway project.