Proposal for comprehensive inspection of Ban Kieng hydropower project

Nhóm PV |

Tuyen Quang - After a field survey, Tung Ba commune proposed to inspect the Ban Kieng hydropower project to ensure the safety of the dam and the environment in the downstream area.

As reported by Lao Dong Newspaper, the construction process of the Ban Kieng hydropower project in Tung Ba commune (Tuyen Quang) has been going on for many years, many items are not yet completed, affecting people in Ban Kieng and Hong Minh villages.

On October 31, information from the People's Council of Tung Ba commune, the unit has just issued a conclusion on a survey of the actual area affected by the Ban Kieng hydropower project.

Van ban thong bao sau kiem tra thuc te tai thuy dien Ban Kieng. Anh: Nhom PV.
Document Notice after actual inspection at Ban Kieng hydropower plant. Photo: PV Group.

According to the report, the cluster of focal works has a designed water reservoir with a capacity of about 500,000m3.

The items of digging foundation holes and drilling for reinforcement and protection of the dambed have been completed according to plan.

The concrete volume of the dam has reached 13,952m3, equivalent to 54% of the progress, the energy route has dug a foundation of 43,890m3 (reaching 70%), the concrete part of the energy route has reached 92.46m3 (3.7%), the factory and transformer station items have not been implemented.

The entire construction site is temporarily suspended. Also through a field survey, the domestic water pipeline in the dam area was damaged.

Khu vuc du an dang trong giai doan hoan thien va hien dang bi tam dung thi cong. Anh: Nhom PV.
The project area is in the completion stage and is currently suspended. Photo: PV Group

In the area behind the dam, rocks and soil from the leveling process and opening pipelines flow down the negative slope, when heavy rain flows down, burying the agricultural land area, canals and damaging the domestic waterway.

The survey results determined that the situation of rocks and soil flowing into the stream bed, causing silting and landslides in rice fields was correct, true to the reflection and recommendation of local people.

Domestic water sources are seriously affected by the construction process in the upstream area, some pipes are broken, tanks are damaged, water is unsanitary and unstable.

The cause was determined to be prolonged heavy rain combined with steep terrain and un placement, unsecured dumping site, causing soil and rocks to flow directly downstream.

From this result, Tung Ba commune requested Ton Tho Agricultural Lam Construction Investment Joint Stock Company to temporarily suspend the construction of items at risk of landslides, urgently overcome and return production land to the people.

Enterprises must repair, dredge water tanks, and supplement pipelines to ensure clean water for households affected in Ban Kieng and Hong Minh villages.

At the same time, the company needs to dredge streams, canals, leveling, embankments to prevent landslides and develop a plan to establish a new dumping site, coordinate with the People's Committee of the commune and the Village Management Board to survey the safe location.

rhhd
The authorities inspect the field and organize a dialogue with the people. Photo: PV Group.

The Tung Ba commune government also requested the enterprise to coordinate in counting the damage, counting and developing a compensation, support and compensation plan for each affected household, to fulfill the commitment.

The People's Committee of the commune is responsible for monitoring, urging the progress of the repair, promptly reporting the problems and coordinating with specialized agencies to assess the current status of the project, environment, and waste dump.

The commune also proposed that the province and relevant departments inspect and evaluate the environmental impact, construction quality and dam safety, and at the same time set up markers to determine the area of affected land and forests for long-term management.

Previously, on October 14, the Department of Industry and Trade of Tuyen Quang province chaired a dialogue meeting between people, commune authorities and investors to clarify recommendations and agree on solutions.

On the side of Ton Tho Agricultural Lam Company, a representative admitted that there was a situation of landslides and lack of water, and said that construction had been temporarily suspended since May 2025. The enterprise is committed to completing all repair contents before October 31.

The Ban Kieng hydropower project is invested by Ton Tho Agricultural Lam Construction Investment Joint Stock Company, with an installed capacity of 3.6MW, started construction around 2005, expected to generate electricity in the first quarter of 2020.

In 2024, the project will be restarted, with a completion date for the third quarter of this year. However, there have been almost no construction activities at the construction site for many months.

Nhóm PV
RELATED NEWS

Water levels of hydroelectric reservoirs in the North on October 28

|

Hydropower reservoirs in the North are flexibly operated according to flood developments, ensuring safety for downstream areas.

The bottom spillway of Hoa Binh hydroelectric reservoir and the bottom spillway of Tuyen Quang hydroelectric reservoir are ordered to be closed

|

1 bottom spillway of Hoa Binh hydroelectric reservoir and 1 bottom spillway of Tuyen Quang hydroelectric reservoir were ordered to close at 5:00 p.m. on October 16.

Lack of water and loss of livelihood while living at the foot of unfinished hydropower plant in Tuyen Quang

|

Tuyen Quang - At the foot of the unfinished hydropower project, dozens of households in Tung Ba commune are living in a state of lack of water, and their cultivated land is being narrowed.

Hanoi proposes to stop organizing fireworks displays on the evening of November 4

|

Hanoi requested the Organizing Committee of the Autumn Fair to stop organizing fireworks displays on the evening of November 4 to share and accompany people in the Central region who were heavily affected by floods.

Bach Mai Hospital, Viet Duc Facility 2 is expected to be inaugurated on December 19

|

The Deputy Prime Minister requested the preparation of human resource plans, promoting the procurement and bidding of equipment for Bach Mai and Viet Duc Hospitals, Facility 2.

Continue to join hands to support people in provinces affected by storms No. 11, No. 12 and floods

|

The Presidium of the Central Committee of the Vietnam Fatherland Front called for continued support for people in the provinces affected by storms No. 11, No. 12 and floods.

Ke Go Lake increases spillway discharge

|

Ha Tinh - Ke Go Lake operator announced that they will increase the overflow flow to the range of 350m3/s - 800m3/s from 5:00 p.m. on October 31, causing the downstream area to worry.

40 years of national renovation bring great achievements, historical stature

|

Prof. Dr. Ta Ngoc Tan emphasized that 40 years of renovation have brought our country great achievements and great historical significance.

Water levels of hydroelectric reservoirs in the North on October 28

Yên San |

Hydropower reservoirs in the North are flexibly operated according to flood developments, ensuring safety for downstream areas.

The bottom spillway of Hoa Binh hydroelectric reservoir and the bottom spillway of Tuyen Quang hydroelectric reservoir are ordered to be closed

Huy Hùng |

1 bottom spillway of Hoa Binh hydroelectric reservoir and 1 bottom spillway of Tuyen Quang hydroelectric reservoir were ordered to close at 5:00 p.m. on October 16.

Lack of water and loss of livelihood while living at the foot of unfinished hydropower plant in Tuyen Quang

Nhóm PV |

Tuyen Quang - At the foot of the unfinished hydropower project, dozens of households in Tung Ba commune are living in a state of lack of water, and their cultivated land is being narrowed.