The reason why the 1,500 billion VND road through Bien Hoa City is under slow construction

HÀ ANH CHIẾN |

Dong Nai - The Bien Hoa City central axis road project with a total investment of 1,500 billion VND, started construction in early 2023, but is 500 days behind schedule.

According to the People's Committee of Dong Nai province, the Bien Hoa City Central Road Project is a key project of the province, and the project's progress has been delayed by 500 days. The reason is that the construction site is stuck, so far only 124 households have been handed over about 66% of the area (20.7 hectares of household land, traffic, rivers and streams). However, the handed over site has not been continuous, leading to the failure to synchronously implement construction items.

Dong Nai Provincial People's Committee requested the Dong Nai Provincial Land Fund Development Center to coordinate with Bien Hoa City People's Committee to urgently carry out compensation and site clearance work, promptly hand over clean land to the investor to carry out construction work, first of all the construction area of ​​Thong Nhat Bridge, Vam Ong An Bridge and branches 1 and 2 of the traffic road section...

Du an duong truc trung tam TP Bien Hoa vuong mat bang, thieu tai dinh cu. Anh tu lieu: HAC
Bien Hoa City central axis road project has land acquisition problems and lacks resettlement. Photo: HAC

Mr. Ngo The An - Director of the Dong Nai Province Traffic Construction Investment Project Management Board said that in the past, the construction contractor mainly only had the construction site for the bridge piers under Cai River. Meanwhile, the construction area of ​​piers T13, pier M2 in Hiep Hoa ward and the area from pier M1 to pier T3 in Thong Nhat ward encountered many difficulties due to not having enough land handed over.

Explaining the delay in handing over the land, a representative of the Dong Nai Province Land Fund Development Center said that the review and resettlement arrangements were carried out by the Bien Hoa City Compensation Council, but to date, the resettlement areas serving the project have not yet been built with infrastructure as originally planned. Therefore, it is difficult to mobilize people to hand over the land.

The project to build the central axis road of Bien Hoa city is 5.4 km long, divided into 2 branches.

In which, branch 1 starts at the intersection of Vo Thi Sau Street and ends at the intersection of Dang Van Tron Street (at An Hao Bridge intersection) with a road section 3.1 km long, 60 m wide, and Thong Nhat Bridge section 563.8 m long, 31 m wide.

Branch 2 has its starting point at the roundabout intersection with branch 1 (Hiep Hoa ward), its ending point is at the intersection of Dang Van Tron street (at the intersection of Buu Hoa bridge head road) with a route length of about 1.7 km, roadbed width of 47 m.

The Bien Hoa City Central Axis Road Project with Thong Nhat Bridge and the road connecting the two ends of the bridge with a total investment of more than VND 1,506 billion was started on January 31, 2023 and is expected to be completed after nearly 3 years of construction.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Deputy Chief of Office of Dong Nai People's Committee appointed Deputy Secretary of Bien Hoa City

|

Mr. Nguyen Phong An - Deputy Chief of Office of Dong Nai Provincial People's Committee was assigned by Dong Nai Provincial Party Committee to hold the position of Deputy Secretary of Bien Hoa City Party Committee.

Merging many wards of Bien Hoa city, Dong Nai province

|

After the merger, Dong Nai province has 11 district-level administrative units and 159 commune-level administrative units.

Failure to hand over sufficient land for Bien Hoa - Vung Tau expressway will result in disciplinary action

|

The Chairman of Dong Nai Provincial People's Committee proposed to reward and discipline communes and wards of Bien Hoa City and Long Thanh District for the progress of Bien Hoa - Vung Tau Expressway.

Official list of 51 wards of Hanoi after the merger

|

Hanoi City has 126 commune-level administrative units, including 51 wards and 75 communes after the arrangement and merger.

Drainage project is under construction, people in Thu Duc City suffer from bad roads and traffic jams

|

HCMC - The Nguyen Duy Trinh drainage project is under construction for a long time, causing the roads to be flooded, muddy, and congested during the rainy season, causing difficulties for people.

Iran fires more than 370 missiles at Israel, US diplomatic facility damaged

|

Iran's heavy missile attacks have caused heavy damage to Israel, and the US diplomatic facility in Tel Aviv has also been affected.

Permanent Vice President of the Vietnam General Confederation of Labor Thai Thu Xuong congratulates Lao Dong Newspaper

|

On the occasion of the 100th anniversary of the Vietnam Revolutionary Press (June 21,25 - June 21, 2025), on the afternoon of June 16, Permanent Vice President of the Vietnam General Confederation of Labor Thai Thu Xuong and a working delegation of the Vietnam General Confederation of Labor came to congratulate the collective of cadres, reporters and employees of Lao Dong Newspaper.

The reason why People's Artist Tu Long apologized to the audience after 6 nights of performance

|

People's Artist Tu Long and many artists were choked up in emotion when witnessing the support of the audience for Call Me by Fire.

Deputy Chief of Office of Dong Nai People's Committee appointed Deputy Secretary of Bien Hoa City

HÀ ANH CHIẾN |

Mr. Nguyen Phong An - Deputy Chief of Office of Dong Nai Provincial People's Committee was assigned by Dong Nai Provincial Party Committee to hold the position of Deputy Secretary of Bien Hoa City Party Committee.

Merging many wards of Bien Hoa city, Dong Nai province

PHẠM ĐÔNG |

After the merger, Dong Nai province has 11 district-level administrative units and 159 commune-level administrative units.

Failure to hand over sufficient land for Bien Hoa - Vung Tau expressway will result in disciplinary action

HÀ ANH CHIẾN |

The Chairman of Dong Nai Provincial People's Committee proposed to reward and discipline communes and wards of Bien Hoa City and Long Thanh District for the progress of Bien Hoa - Vung Tau Expressway.