Working at Long Thanh airport project

Hà Anh Chiến |

From a red basalt land, to date, Long Thanh airport has taken on the clear shape of a modern international air transshipment hub of the region.

Airport scale of 5,000ha

The Long Thanh airport project has an area of more than 5,000ha located in Long Thanh ward, Dong Nai City. To implement the project, Dong Nai City must recover a land area of 5,000ha with more than 5,000 affected households. Among them, more than 4,300 households are completely cleared and are subject to resettlement arrangement.

Since 2015, Lao Dong Newspaper reporters have had the first articles reflecting the people's desire for the project to be implemented soon. The super project has been planned for many years and households in the project area are also in the mindset of wanting to be relocated soon to give up land for the country's socio-economic development project.

In 2020, Lao Dong Newspaper reporters in the delegation including many other resident reporters also coordinated with Dong Nai City People's Committee to propagate to people in the relocation and site clearance of the Long Thanh airport project. Lao Dong Newspaper reporters directly went to the core area of the Long Thanh airport project to record the atmosphere of people preparing to relocate to give up land to build the airport; met with "village elders" and heard their confidences about the formation of villages and hamlets with vast rubber plantation areas feeding many generations of people.

Mr. Nguyen Duc Liem is one of the "village elders" who have lived in the core area of the Long Thanh airport project since 1975. Mr. Liem said: "When I came here to start a business, the whole area was still a dense forest with many ancient trees that one person could not embrace, and gradually many people came to live and establish villages. However, when the State had a policy to recover land to build an airport, my family all supported it.

Phóng viên báo Lao Động tác nghiệp tại gói thầu 5.10 - Nhà ga hành khách sân bay Long Thành. Ảnh: HAC
Lao Dong Newspaper reporters working at package 5. 10 - Long Thanh airport passenger terminal. Photo: HAC

In early 2021, when the Long Thanh airport project was officially started and site clearance for thousands of hectares was completed, it created an open, vast area of all basalt red soil. From afar, looking at the rollers and bulldozers that are only small like black dots, traveling kilometers without a single green tree, reporters worked in hot weather, drizzling rain.

Mr. Nguyen Van Tuan - a resident reporter in Dong Nai - shared: "Outside the construction site, the sun is harsh, the wind is strong, I wear very thick clothes, wrapped a scarf around my face but still burns".

During the reporting process, reporters also followed the working group of Long Thanh district (old) and Vietnam Airports Corporation (ACV) wading through streams and rubber forests to record the handover of clean land so that contractors could immediately proceed with the construction of ground leveling and drainage packages.

The shape of a modern super station gradually reveals itself

To date, in the middle of the red basalt land, the largest international airport construction site in the country is entering the final sprint stage. The modern, magnificent super terminal is gradually being "drawn" by the hands of thousands of engineers and workers working day and night to put it into commercial operation by the end of 2026 as required by the Government.

Long Thanh International Airport is built on an area of more than 5,000ha in Long Thanh ward, Dong Nai city. The project has a total estimated investment of more than 16 billion USD, divided into 3 phases. In which, phase 1 is more than 5.4 billion USD, with a capacity of 25 million passengers/year and 1.2 million tons of cargo/year. After completing all phases, Long Thanh International Airport will reach a capacity of up to 100 million passengers/year and become the largest airport in our country, with transit function in Southeast Asia, competing with major airports in the world.

Hà Anh Chiến
RELATED NEWS

Long Thanh airport is about to open, An Phu intersection is still messy

|

Ho Chi Minh City - Long Thanh airport is about to open, connecting routes are speeding up, but An Phu intersection is still unfinished, risking becoming a "bottleneck" on the road to the airport.

3 roads connecting Long Thanh airport hand over more than 250ha of land

|

Dong Nai - Three roads connecting Long Thanh airport (roads 769, 773 and 770B) are under construction, and more than 250ha of land has been handed over.

Workers race to catch up with Long Thanh airport's trial operation in September

|

Dong Nai - Long Thanh Airport is undergoing trial operation from September 2026, in which the passenger terminal package is being raced for progress by thousands of workers.

Fastest route from the center of Ho Chi Minh City to Long Thanh airport

|

Ho Chi Minh City - When Long Thanh airport comes into operation, Ho Chi Minh City residents will mainly connect through the Ho Chi Minh City - Long Thanh expressway, Ring Road 3 and Ben Luc - Long Thanh expressway.

2 traffic routes connecting Long Thanh airport are basically completed

|

Dong Nai - The total output of component project 3 of Long Thanh airport reached about 77.85%, of which 2 connecting traffic routes have been basically completed.

Long Thanh Airport: Some bidding packages exceed 90%, new bidding packages reach 36%

|

Dong Nai - Many main construction packages at Long Thanh airport have reached over 90%, including a package that has been basically completed.

Developing a detailed plan for 5,000ha of Long Thanh airport, preparing for phase 2

|

Dong Nai - Airports Corporation of Vietnam (ACV) is implementing detailed planning for the Long Thanh airport project on a total area of 5,000ha.

Lien Khuong airport completes runway, counting down the days to welcome return flights

|

Lam Dong - After more than 5 months of temporary closure for upgrading and repairing, Lien Khuong airport has completed more than 99% of its volume, ready to reopen on August 19.

Long Thanh airport is about to open, An Phu intersection is still messy

MINH QUÂN |

Ho Chi Minh City - Long Thanh airport is about to open, connecting routes are speeding up, but An Phu intersection is still unfinished, risking becoming a "bottleneck" on the road to the airport.

3 roads connecting Long Thanh airport hand over more than 250ha of land

HÀ ANH CHIẾN |

Dong Nai - Three roads connecting Long Thanh airport (roads 769, 773 and 770B) are under construction, and more than 250ha of land has been handed over.

Workers race to catch up with Long Thanh airport's trial operation in September

HÀ ANH CHIẾN |

Dong Nai - Long Thanh Airport is undergoing trial operation from September 2026, in which the passenger terminal package is being raced for progress by thousands of workers.

Fastest route from the center of Ho Chi Minh City to Long Thanh airport

MINH QUÂN |

Ho Chi Minh City - When Long Thanh airport comes into operation, Ho Chi Minh City residents will mainly connect through the Ho Chi Minh City - Long Thanh expressway, Ring Road 3 and Ben Luc - Long Thanh expressway.

2 traffic routes connecting Long Thanh airport are basically completed

HÀ ANH CHIẾN |

Dong Nai - The total output of component project 3 of Long Thanh airport reached about 77.85%, of which 2 connecting traffic routes have been basically completed.

Long Thanh Airport: Some bidding packages exceed 90%, new bidding packages reach 36%

HÀ ANH CHIẾN |

Dong Nai - Many main construction packages at Long Thanh airport have reached over 90%, including a package that has been basically completed.

Developing a detailed plan for 5,000ha of Long Thanh airport, preparing for phase 2

HÀ ANH CHIẾN |

Dong Nai - Airports Corporation of Vietnam (ACV) is implementing detailed planning for the Long Thanh airport project on a total area of 5,000ha.