belt 1

Enforced site clearance for Ring Road 1 project

|

Hanoi - Despite propaganda and mobilization, households in Giang Vo ward still do not hand over the land for the Ring Road 1 project, and the authorities have to force it.

357 households that have not yet handed over the land to build Ring Road 1 will be forced to work overnight

|

To ensure the progress of site clearance for Ring Road 1, Lang Ward proposed that the Hanoi People's Committee carry out a shortened process.

Banning Ring Road 1 motorbikes: Deputy Director of Hanoi Department of Construction talks about support levels for people

|

To make people and businesses feel secure in converting to green vehicles, Hanoi is studying and implementing a comprehensive support policy system.

24 hours before site clearance for Ring Road 1

|

Hanoi - Households in Giang Vo ward who deliberately do not hand over the land for the Ring Road 1 project will be forced to reclaim their land tomorrow (December 10).

As the deadline approaches, some households have not yet handed over the land for the Ring Road 1 project

|

Hanoi - In O Cho Dua ward, there are 16 plans approved for compensation but people have not yet handed over the site for the Ring Road 1 project.

Ring Road 1 speeds up after many years of delay, people urgently liquidate and relocate assets

|

Hanoi - People are rushing to dismantle, relocate and hand over the site, contributing to speeding up the progress of the Ring Road 1 project, Hoang Cau - Voi Phuc section.

Hanoi cuts off electricity and water completely, prepares to enforce land acquisition for Ring Road 1

|

Hanoi - Giang Vo Ward will cut off electricity and water to households who deliberately do not hand over the land for the Ring Road 1 project on December 5, and will forcibly reclaim the land on December 10.

Hanoi demolishes a series of works to build Ring Road 1

|

Hanoi - Machinery is mobilized to dismantle many works to serve the construction of the Ring Road 1 project, Hoang Cau - Voi Phuc section, with a capital of more than 7,200 billion VND.

Hanoi officially sets the completion date of the Ring Road 1 project

|

Hanoi has adjusted the implementation time of the Ring Road 1 project, Hoang Cau - Voi Phuc section, to the end of 2026, due to land clearance problems.

Many advantages in site clearance for Ring Road 1 project

|

Hanoi - Site clearance for the Ring Road 1 project is being urgently implemented to complete before December 15 according to the city's direction.

Directive of the Hanoi Secretary regarding site clearance for Ring Road 1

|

Secretary of the Hanoi Party Committee Nguyen Duy Ngoc requested to ensure the completion of all site clearance for Ring Road 1 before December 15.

Hanoi Chairman gives urgent instructions on the roadmap to ban motorbikes from using gasoline in Ring Road 1

|

The Chairman of the Hanoi People's Committee requested that according to his authority, motorbikes and mopeds using fossil fuels in Ring Road 1 be banned.

Hanoi to ban plastic at once in Ring Road 1, people struggle to find an alternative

|

Hanoi will pilot the non-use of disposable plastic items at restaurants and eateries in Ring Road 1 from the fourth quarter of 2025.

Current status of Hanoi Ring Road 1 will ban gasoline vehicles from July 2026

|

Hanoi is about to ban gasoline motorbikes from traveling on Ring Road 1, including the Hoang Cau - Voi Phuc section, the road considered "the most expensive on the planet".

Hanoi promotes site clearance to implement Ring Road 1 project

|

Hanoi - Currently, Dong Da and Ba Dinh districts are stepping up site clearance (GPMB) to serve the Ring Road 1 project.