belt 1
Enforced site clearance for Ring Road 1 project
|
Hanoi - Despite propaganda and mobilization, households in Giang Vo ward still do not hand over the land for the Ring Road 1 project, and the authorities have to force it.
357 households that have not yet handed over the land to build Ring Road 1 will be forced to work overnight
|
To ensure the progress of site clearance for Ring Road 1, Lang Ward proposed that the Hanoi People's Committee carry out a shortened process.
Banning Ring Road 1 motorbikes: Deputy Director of Hanoi Department of Construction talks about support levels for people
|
To make people and businesses feel secure in converting to green vehicles, Hanoi is studying and implementing a comprehensive support policy system.
24 hours before site clearance for Ring Road 1
|
Hanoi - Households in Giang Vo ward who deliberately do not hand over the land for the Ring Road 1 project will be forced to reclaim their land tomorrow (December 10).
As the deadline approaches, some households have not yet handed over the land for the Ring Road 1 project
|
Hanoi - In O Cho Dua ward, there are 16 plans approved for compensation but people have not yet handed over the site for the Ring Road 1 project.
Ring Road 1 speeds up after many years of delay, people urgently liquidate and relocate assets
|
Hanoi - People are rushing to dismantle, relocate and hand over the site, contributing to speeding up the progress of the Ring Road 1 project, Hoang Cau - Voi Phuc section.
Hanoi cuts off electricity and water completely, prepares to enforce land acquisition for Ring Road 1
|
Hanoi - Giang Vo Ward will cut off electricity and water to households who deliberately do not hand over the land for the Ring Road 1 project on December 5, and will forcibly reclaim the land on December 10.
Hanoi demolishes a series of works to build Ring Road 1
|
Hanoi - Machinery is mobilized to dismantle many works to serve the construction of the Ring Road 1 project, Hoang Cau - Voi Phuc section, with a capital of more than 7,200 billion VND.
Hanoi officially sets the completion date of the Ring Road 1 project
|
Hanoi has adjusted the implementation time of the Ring Road 1 project, Hoang Cau - Voi Phuc section, to the end of 2026, due to land clearance problems.
Many advantages in site clearance for Ring Road 1 project
|
Hanoi - Site clearance for the Ring Road 1 project is being urgently implemented to complete before December 15 according to the city's direction.
Directive of the Hanoi Secretary regarding site clearance for Ring Road 1
|
Secretary of the Hanoi Party Committee Nguyen Duy Ngoc requested to ensure the completion of all site clearance for Ring Road 1 before December 15.
Hanoi Chairman gives urgent instructions on the roadmap to ban motorbikes from using gasoline in Ring Road 1
|
The Chairman of the Hanoi People's Committee requested that according to his authority, motorbikes and mopeds using fossil fuels in Ring Road 1 be banned.
Hanoi to ban plastic at once in Ring Road 1, people struggle to find an alternative
|
Hanoi will pilot the non-use of disposable plastic items at restaurants and eateries in Ring Road 1 from the fourth quarter of 2025.
Current status of Hanoi Ring Road 1 will ban gasoline vehicles from July 2026
|
Hanoi is about to ban gasoline motorbikes from traveling on Ring Road 1, including the Hoang Cau - Voi Phuc section, the road considered "the most expensive on the planet".
Hanoi promotes site clearance to implement Ring Road 1 project
|
Hanoi - Currently, Dong Da and Ba Dinh districts are stepping up site clearance (GPMB) to serve the Ring Road 1 project.