Dong Nai deploys relocation of power grid infrastructure under high-speed railway project

HÀ ANH CHIẾN |

Dong Nai - The Provincial People's Committee assigned units to relocate the power grid under 100kV and over 110kV of the high-speed railway project on the North - South axis.

On October 31, the People's Committee of Dong Nai province issued an official dispatch to deploy the relocation of power grid infrastructure for the high-speed railway project on the North-South axis, the section passing through Dong Nai province.

Accordingly, the Chairman of the Provincial People's Committee opinions that for the power grid with a voltage of less than 110kV (belonging to the independent component project on compensation and site clearance managed by the province), the Provincial Land Fund Development Center should preside over and coordinate with Dong Nai Power Company and related units to conduct a detailed survey, develop a compensation, support or relocation plan according to regulations; Responsible for preparing a relocation design dossier, submitting for approval and organizing the relocation and return of power grid infrastructure in accordance with regulations.

Tren dia ban tinh Dong Nai se duoc bo tri 1 nha ga hanh khach duong sat toc do cao Bac - Nam trong khu vuc cang hang khong quoc te Long Thanh. Anh: HAC
In Dong Nai province, a North-South high-speed railway passenger terminal will be arranged in the Long Thanh international airport area. Photo: HAC

For power grids of 110kV or more (belonging to sub-projects implemented by Vietnam Electricity Group), the People's Committees of wards and communes: Hang Gon, Long Thanh, Xuan Loc, Xuan Hoa, Nhon Trach, Xuan Phu, Xuan Que, Xuan Dinh, Cam My, Xuan Duong, Long Phuoc, An Phuoc organize the implementation, closely coordinate with Vietnam Electricity Group and management and operation units (Eastern Power Transmission 1) to relocate works according to regulations; Focus on land acquisition, handover of relocation pillar foundation locations, ensuring the relocation progress of the Group.

The project is cross-led with 6 locations of 500kV and 220kV transmission lines managed by Eastern Power Transmission 1 under the National Power Transmission Corporation (EVNNPT); There are 5 110kV grid cross-location locations and 35 medium and low-volume grid cross-location locations under the management of Dong Nai Power Company and customers.

HÀ ANH CHIẾN
RELATED NEWS

Hopefully, the site clearance milestone for the high-speed railway project will be handed over soon

|

The investor has not yet handed over the site clearance markers for the high-speed railway project, so the Ha Tinh functional sector is concerned about great pressure as time is getting faster.

Khanh Hoa needs VND 8,626 billion for site clearance for high-speed railway

|

Khanh Hoa needs to allocate VND 8,626 billion from the central budget to implement compensation and site clearance for the high-speed railway project

The North-South high-speed railway project through 2 communes in Dong Nai coincides with the heart of route 769E

|

Dong Nai - The People's Committees of wards and communes determined the number of households that had to be relocated and resettled for the high-speed railway project on the North-South axis.

Complicated floods, General Luong Tam Quang requests to protect people's lives above all

|

Amid complicated floods in the Central region, General Luong Tam Quang requested the police force to rescue people and protect people's lives above all, first of all.

Bach Mai Hospital, Viet Duc Facility 2 is expected to be inaugurated on December 19

|

The Deputy Prime Minister requested the preparation of human resource plans, promoting the procurement and bidding of equipment for Bach Mai and Viet Duc Hospitals, Facility 2.

Continue to join hands to support people in provinces affected by storms No. 11, No. 12 and floods

|

The Presidium of the Central Committee of the Vietnam Fatherland Front called for continued support for people in the provinces affected by storms No. 11, No. 12 and floods.

Ke Go Lake increases spillway discharge

|

Ha Tinh - Ke Go Lake operator announced that they will increase the overflow flow to the range of 350m3/s - 800m3/s from 5:00 p.m. on October 31, causing the downstream area to worry.

Jack's return after a series of scandals

|

Jack has announced a temporary hiatus, but is there any chance of this male singer returning after the scandal?

Hopefully, the site clearance milestone for the high-speed railway project will be handed over soon

TRẦN TUẤN |

The investor has not yet handed over the site clearance markers for the high-speed railway project, so the Ha Tinh functional sector is concerned about great pressure as time is getting faster.

Khanh Hoa needs VND 8,626 billion for site clearance for high-speed railway

Hữu Long |

Khanh Hoa needs to allocate VND 8,626 billion from the central budget to implement compensation and site clearance for the high-speed railway project

The North-South high-speed railway project through 2 communes in Dong Nai coincides with the heart of route 769E

HÀ ANH CHIẾN |

Dong Nai - The People's Committees of wards and communes determined the number of households that had to be relocated and resettled for the high-speed railway project on the North-South axis.