The traffic intersection on the expressway worth more than VND34,000 billion will start construction in 2025

VIÊN NGUYỄN |

Quang Ngai - Vietnam Expressway Corporation will continue to implement the construction of the Tri Binh - Dung Quat intersection in the second quarter of 2025.

Unfinished for nearly 7 years

Since September 2018, the Da Nang - Quang Ngai Expressway (Km0+000 - Km139+204) has passed through 3 provinces and cities: Da Nang, Quang Nam, Quang Ngai with a total investment of more than 34,000 billion VND, officially opening the entire route. The project is invested by Vietnam Expressway Corporation (VEC).

Although the expressway has been open to traffic for nearly 7 years, the Tri Binh - Dung Quat intersection, located in Binh Nguyen and Binh Chanh communes (Binh Son district, Quang Ngai province) is still unfinished and desolate. This is the last of the 8 intersections on the entire Da Nang - Quang Ngai expressway that have not been connected, despite being one of the most important intersections.

Kiem tra nen dia chat tai du an nut giao Tri Binh - Dung Quat. Anh: Vien Nguyen.
Checking the geological foundation at the Tri Binh - Dung Quat intersection project. Photo: Vien Nguyen.

The intersection of Tri Binh - Dung Quat belongs to the A3 bidding package by Jiangsu Contractor (China). Bidding package A3 is 10.6 km long, with a total value of about VND 1,360 billion from the World Bank loan (WB). In November 2018, VEC admitted to the highway rotation with Tri Binh - Dung Quat port, which was subsided in excess of the permitted level. According to the plan, by June 2019, the contractor will overcome the subsidence, but so far the project is still "standing still".

Strive to complete within 6 months

According to the reporter's source, the Ministry of Transport (now the Ministry of Construction) has received a written request from the People's Committee of Quang Ngai Province related to the Da Nang - Quang Ngai Expressway Project. The provincial People's Committee has sent a written request to VEC to resolve the remaining shortcomings such as: site clearance, investment in completing the intersection of Tri Binh - Dung Quat, soon implementing stops on the highway. However, so far has not been resolved. Quang Ngai province has asked the Ministry of Construction to direct VEC to implement soon.

Nut giao Tri Binh - Dung Quat dau tu xay dung dang do roi bo hoang gan 7 nam qua. Anh: Vien Nguyen.
The Tri Binh - Dung Quat intersection has been under construction and then abandoned for nearly 7 years. Photo: Vien Nguyen.

According to VEC's report, in the recommendations of Quang Ngai province, there are still some outstanding issues that are being handled. VEC is directing consultants to complete the investment project adjustment dossier to submit to the Ministry of Construction for approval in March 2025, as a basis for implementing the remaining items of the project, including compensation, support and resettlement.

According to the report, the total cost of site clearance for the section passing through Quang Ngai province will be updated by VEC into the total adjusted investment of the project.

Regarding the investment in completing the intersection of Binh - Dung Quat, VEC will arrange capital, submit to the Ministry of Construction for approval in the investment project adjustment dossier, to continue the construction in the second quarter of 2025. It is expected that the project will be completed within 6 months (before December 2025), in accordance with the direction of the Prime Minister.

For the investment in the stations on the North - South highway in the East in general and the Da Nang - Quang Ngai highway in particular, the Ministry of Construction has approved the location, location, construction scale and direction. VEC will arrange investment capital, propose the form of investment stations and submit to the Ministry of Construction for approval in the investment project adjustment dossier for construction and completion in the second quarter of 2027.

VIÊN NGUYỄN
TIN LIÊN QUAN

The intersection connecting Nhon Trach Bridge with Ho Chi Minh City - Long Thanh Expressway is about to be completed

|

In order to ensure connection with Nhon Trach Bridge on April 30, the construction of the Ring Road 3 intersection connecting Ho Chi Minh City - Long Thanh - Dau Giay Expressway is being accelerated.

Busy leveling the ground, constructing the Vinh Hao - Phan Thiet expressway rest stop

|

Binh Thuan - Dump trucks carrying materials and bulldozers are busy at the construction site of the Vinh Hao - Phan Thiet expressway rest stop at Km205.

Preparing to invest 35,000 billion VND in Quang Ngai - Kon Tum Expressway

|

Kon Tum - In order for the expressway project to be constructed soon, the province will proactively implement site clearance and resettlement arrangements for people.

Reasons for choosing Bac Giang City as the administrative center of Bac Ninh province after the merger

|

Bac Ninh - The project to reorganize Bac Ninh and Bac Giang provinces clearly states the reasons for choosing Bac Giang city as the administrative center after the merger.

Updated gold price at the end of session 19.4: Shocking decrease, risks still lie

|

Updated gold price at the end of the session on September 19: Domestic gold prices decreased by up to 6 million VND/tael. The risk is still tiem nang when the difference between buying and selling is too high.

Nghe An has many options for naming new communes after the arrangement

|

Nghe An - Some localities named new communes after districts with serial numbers, some other localities named them with historical and traditional cultural elements.

The Ministry of Public Security informs about new features on VNeID for flying

|

The VNeID application has just integrated a new feature to serve passengers getting on a plane from buying tickets, going through security checkpoints... the entire process without paperwork.

List of 65 expected commune-level administrative units in Thai Binh after the reorganization

|

Thai Binh - According to the draft project, after the arrangement, the whole Thai Binh province will now decrease from 242 to 65 commune-level administrative units.

The intersection connecting Nhon Trach Bridge with Ho Chi Minh City - Long Thanh Expressway is about to be completed

Anh Tú |

In order to ensure connection with Nhon Trach Bridge on April 30, the construction of the Ring Road 3 intersection connecting Ho Chi Minh City - Long Thanh - Dau Giay Expressway is being accelerated.

Busy leveling the ground, constructing the Vinh Hao - Phan Thiet expressway rest stop

Duy Tuấn |

Binh Thuan - Dump trucks carrying materials and bulldozers are busy at the construction site of the Vinh Hao - Phan Thiet expressway rest stop at Km205.

Preparing to invest 35,000 billion VND in Quang Ngai - Kon Tum Expressway

THANH TUẤN |

Kon Tum - In order for the expressway project to be constructed soon, the province will proactively implement site clearance and resettlement arrangements for people.