Society
Latest forecast of the path of storm No. 14 Fung-wong in the next 24 hours
|
The meteorological agency said that storm No. 14 Fung-wong is currently at level 13, gusting to level 16 and moving slowly in the eastern sea area of the northern East Sea.
Forecasting the dangerous area in the next 24 hours of storm Fung-wong, the Ministry of Natural Resources and Environment sent a telegram to 13 provinces and cities
|
Provinces from Quang Ninh to Dak Lak need to proactively respond to storm No. 14 Fung-wong.
Water levels of hydroelectric reservoirs in the North on November 10
|
Hydropower reservoirs in the North are flexibly operated according to flood developments, ensuring safety for downstream areas.
Rewarding 2 people of Ly Son, Quang Ngai for their bravery in saving people in the storm
|
On the morning of November 10, the People's Committee of Ly Son Special Zone, Quang Ngai organized a special reward for two people and a boat owner for their brave actions in saving people in storm No. 13.
Drilling and pumping chemicals to reinforce the body of the irrigation dam containing 1.7 million m3 of water in Lam Dong
|
Lam Dong - The technical unit has conducted a drilling and exploration to assess the structure of the Cay An irrigation lake dam to pump waterproof chemicals and reinforce the dam body.
Can Tho - Ca Mau Expressway continues to be paved with asphalt concrete
|
Can Tho - On January 2-3, 2025, the Can Tho - Ca Mau expressway continued to be paved with asphalt concrete with a length of 800m.
Long An province directs handling of slow relocation of slaughterhouse
|
The Chairman of Long An province has just issued instructions regarding the slow relocation of many livestock slaughterhouses in Duc Hoa district.
Emergency repair of landslide on residential road in Hue
|
HUE - Pouring soil and grading crushed stone to urgently repair about 200m of landslide-affected residential road to ensure safety and serve people's travel needs.
Erosion repair on Da Nang beach expected in 7 days
|
Da Nang - To overcome the landslide of My Khe beach, Son Tra district, the City People's Committee mobilized hundreds of people to build temporary barriers.
Appearance of the 118 billion VND road to Phan Thiet airport just opened to traffic
|
Binh Thuan - The Phan Thiet airport access road project (phase 2) has been opened to traffic; vehicles are moving smoothly after nearly 1 year of construction.
Couple in Yen Bai drowned while fishing
|
While fishing on the river, a couple in Tran Yen district, Yen Bai province unfortunately had their boat capsized, leading to their deaths.
The final stretch on the billion-dollar route through Thai Nguyen
|
Thai Nguyen - After 3 years of construction, the Ring Road V project through Phu Binh district has entered the final stage. When completed, it will help make travel convenient and easy.
Proposal for 4,800 billion VND project to supply raw water to 3 provinces in the West
|
Western Region - The project provides raw water for the three provinces of Ca Mau - Bac Lieu - Soc Trang, with a total investment of 4,800 billion VND in phase 1.
Bustling largest fishing port in Tuyen Quang hydroelectric reservoir
|
Not far from Tuyen Quang Hydropower Plant, Na Hang fishing wharf becomes bustling in the afternoon, which is also the time when shrimp and fish caught naturally throughout the lake are transferred.
Hai Phong fined 31,600 alcohol concentration violations in 2024
|
Hai Phong authorities have penalized 31,660 cases of drivers violating alcohol concentration in 2024.
Proposed 12,800 billion VND project to solve traffic jams on National Highway 51
|
Dong Nai - Ho Chi Minh City Infrastructure Investment Joint Stock Company proposed a 12,800 billion VND project to build an elevated road along National Highway 51 from Vung Tau intersection - Gate 11.
Car catches fire on highway, driver luckily escapes
|
HCMC - A male driver was driving a pickup truck on the HCMC - Long Thanh - Dau Giay highway when it suddenly caught fire.
The two most polluted times of the day
|
During the day, air pollution levels fluctuate, concentrated between 6-8am and 5-7pm.
Bustling atmosphere at Phung Khoang Park on New Year's Day
|
In the early days of 2025, groups of workers were busy constructing the Phung Khoang Lake Park project (Hanoi) with an excited spirit and enthusiastic efforts.
30 months of construction of highway through 3 northern provinces
|
If an investor is found in the first quarter, the 113km Ring Road 4 expressway will start construction in the second quarter of 2025 and be completed after 30 months of construction.