Dong Dang - Tra Linh Expressway
Efforts to maintain the pace of expressway construction in the face of gasoline and oil price fluctuations
|
Lang Son - Fluctuations in gasoline supply are putting pressure on the Dong Dang - Tra Linh expressway construction site.
The army is mobilized to participate in the construction of the Dong Dang - Tra Linh expressway
|
Cao Bang - 107 officers and soldiers of the army are assigned to participate in the construction of the Dong Dang - Tra Linh expressway.
Huu Nghi - Chi Lang expressway rushes in spring, 2,599 personnel race for progress
|
Lang Son - In the early days of the new year, when many places are still in the spring travel atmosphere, the large construction site of the Huu Nghi - Chi Lang expressway has resounded with the sound of machines.
Tet without holidays at the expressway construction site connecting 2 border provinces
|
The Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway has started construction from the 3rd day of Tet to ensure progress.
Dong Dang - Tra Linh expressway not yet temporarily circulated during the Lunar New Year
|
Cao Bang - Dong Dang - Tra Linh is one of the 2 expressways planned by the Ministry of Construction to organize temporary traffic.
89,000 m3 of excess land on the expressway is utilized for residential areas in Lang Son
|
Lang Son - Excess soil and rocks during the construction of the Dong Dang - Tra Linh expressway are used for construction at Pac Luong residential area.
Phase 1 of Dong Dang - Tra Linh route receives completion order in 2026
|
Cao Bang - The Minister of Construction has just paid a visit and directed the construction progress of the Dong Dang - Tra Linh expressway.
Lessons learned in the construction of the Dong Dang - Tra Linh expressway
|
Cao Bang - In the process of deploying the Dong Dang - Tra Linh expressway, the locality has drawn many important lessons learned.
Dong Dang - Tra Linh Expressway is as beautiful as a painting before the "opening" date
|
In just 2 days, the Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway will officially open the route, opening up opportunities for the Northeastern provinces.
85km of foundation and 20km of asphalt paving will be opened on the Dong Dang - Tra Linh Expressway
|
Cao Bang - At the Dong Dang - Tra Linh expressway construction site, workers are working overtime day and night to open the technical route in time.
Body of Dong Dang - Tra Linh Expressway construction officer swept away by flood found
|
Cao Bang - The body of one of the three officers working on the Dong Dang - Tra Linh expressway swept away by floodwaters has been found.
Identities of 3 officers constructing the Dong Dang - Tra Linh expressway swept away by flood
|
Cao Bang - 3 Dong Dang - Tra Linh construction officers were swept away by floodwaters and went missing.
3 workers constructing the Dong Dang - Tra Linh Expressway were swept away by floodwaters and went missing
|
Cao Bang - Floodwaters poured down too quickly, sweeping through the Dong Dang - Tra Linh Expressway project management center, leaving 3 people missing.
The rainy season is approaching, the resettlement area of tens of thousands of billion VND expressway is still on paper
|
Lang Son - Although people have given up land to serve the expressway, up to now, the resettlement area has not been started, while the rainy season is approaching.
Progress of relocation of a series of electric poles to serve the construction of the Dong Dang - Tra Linh expressway
|
Cao Bang - Of the 24 110kV high-voltage power poles that had to be relocated, none had been relocated.